U.S. energy firm Equitrans Midstream delayed the estimated completion of its Mountain Valley natural gas pipeline from West Virginia to Virginia to the second quarter from the first quarter due in part to adverse weather in January.
The company also boosted the projected cost to complete the project to around $7.57 billion-$7.63 billion, up from a prior estimate of about $7.2 billion.
Equitrans spoke about Mountain Valley in its fourth earnings report, which beat estimates.
Mountain Valley is the only big gas pipeline under construction in the U.S. Northeast. It has encountered numerous regulatory and court fights that have stopped work several times since construction began in 2018.
The pipe, which is key to unlocking gas supplies from Appalachia, the nation's biggest shale gas-producing region, needed a bill from the U.S. Congress that was signed into law by the president and help from the Supreme Court before it could restart construction.
In its earnings release, Equitrans CEO Diana Charletta said "construction crews encountered adverse weather conditions, including precipitation well above 20-year averages."
"These conditions were far worse and longer in duration than anticipated, imposing a significant impact on productivity, which, in turn, impeded our ability to reduce construction headcount," Charletta said.
Delays and cost overruns are nothing new for Mountain Valley.
When Mountain Valley started construction in February 2018, Equitrans estimated the 2 Bcf/d project would cost about $3.5 billion and enter service by late 2018.
The 303-mile (488-kilometre) Mountain Valley project is owned by units of Equitrans, the lead partner building the pipe with a roughly 49% interest, NextEra Energy, Consolidated Edison, AltaGas and RGC Resources. Equitrans will operate the pipeline.
Separately, Equitrans Executive Chairman Thomas Karam said in the earnings release that the "Board of Directors has been engaged in a process with third parties that have expressed interest in strategic transactions with our company."
He said the board has engaged outside advisors and the process is ongoing, noting "There is no guarantee that any transaction will result from this process."
Recommended Reading
TotalEnergies to Invest $400MM in LPG
2024-05-14 - TotalEnergies is investing more than $400 million into LPG to provide more than 100 million people in Africa and Asia access to clean cooking methods by 2030.
EOG Resources Wildcatting Veteran Billy Helms to Retire
2024-04-02 - Joining an EOG Resources predecessor in 1981, Helms is among the pre-1986-oil-bust generation who later found success in shale.
TotalEnergies Eyes Suriname FID by Year-end 2024
2024-04-29 - France’s TotalEnergies and U.S. partner APA Corp. look to place their long lead orders ahead of a final investment decision related to their joint development offshore Suriname in Block 58.
Chevron Adds to Carbon Capture Tech Portfolio with ION Investment
2024-04-04 - Chevron New Energies led a funding round that raised $45 million in Series A financing for ION Clean Energy, according to a news release.
ProPetro to Provide eFrac Services to Exxon’s Permian Operations
2024-04-29 - ProPetro has entered a three-year agreement to provide electric hydraulic fracturing services for Exxon Mobil’s operations in the Permian Basin.