Williams Cos. has yet to nail down a start date for the Louisiana Energy Gateway pipeline project, a month after the project’s completion date was set back from the fourth quarter of 2024.
The Louisiana Energy Gateway is designed to take natural gas from the Haynesville Shale in Arkansas, Louisiana and Texas to developing LNG export terminals on the Louisiana coast. When opened on its now expected completion date in 2025, the line will carry 1.8 Bcf/d.
Progress is still being made, said Williams CEO Alan Armstrong during a March 19 press conference at CERAWeek by S&P Global. The company has had to adjust its pipeline route plans following a dispute with Energy Transfer.
“We have pushed that back from a timing standpoint,” Armstrong said. “But we are pushing ahead and the project’s actually going fairly well.”
The delay can be traced to a dispute between Williams and Energy Transfer, which became public in mid-February. In the company’s investor conference call, Energy Transfer co-CEO Thomas Long noted that the company had been accused of stifling competition by refusing right-of-way access on three projects slated to cross the company’s pipelines.
Williams COO Michael Dunn said Energy Transfer was using its easements to block companies from their preferred pipeline pathways. Since then, Williams has adjusted its plans and remains optimistic the project will be completed.
“We've been able to reroute around some of those hurdles,” Armstrong said. “And so we are pushing ahead.”
Recommended Reading
Kimmeridge’s Mark Viviano on Reshaping the Energy Sector, SilverBow-Crescent Deal
2024-05-16 - Kimmeridge Energy Engagement Partners’ Mark Viviano says the company is evaluating the Crescent Energy and SilverBow Acquisition and how Kimmeridge played a key role in transforming the shale sector in this Hart Energy Exclusive interview.
Oil, Gas Groups Sue BLM to Block Increased Federal Drilling Fees
2024-05-16 - Under new U.S. Bureau of Land Management rules, royalty rates will jump to 16.67% from 12.5% and minimum lease bonds will increase to $150,000 from $10,000, which industry groups say will deter future oil and gas development.
SilverBow Resets Shareholder Meeting After $2.1B Crescent Deal
2024-05-16 - SilverBow Resources said it will adjourn its May 21 shareholders’ meeting until May 29 following Crescent Energy’s agreement to buy the Eagle Ford operator.
SUPER DUG Shale 4.0 Era about Building Scale- Rystad
2024-05-16 - The Shale 3.0 era or capital discipline era will be followed by the Shale 4.0 era, which will see companies focused on building scale, according to Rystad Energy Senior Shale Analyst Matthew Bernstein.
BPX Looks to Ramp US Production Over 60% by 2030
2024-05-16 - BPX Energy is looking to boost its U.S. production over 60% by 2030 as it considers bringing online a fourth processing facility in the Permian by mid-year 2025, Clark Edwards, the company’s vice president of development, said during SUPER DUG in Fort Worth.