Challenging as it is, the Haynesville Shale’s technical hurdles propel drilling and completions technology development that benefits the wider energy industry.
The Haynesville Shale, with its high temperatures and high pressures, is “not for the faint of heart,” Neil Modeland, Halliburton’s senior business development technology manager, said at Hart Energy’s DUG GAS+ Conference and Expo in Shreveport, Louisiana.
High temperatures, he said, have made it difficult to acquire completion diagnostics.
“Temperature has made it difficult for any sensors, any diagnostic measurements, to go down there,” he said, noting the need to rotate casing also rules out fiber optics on the backside of casing.
However, disposable fiber can be pumped into offset wells to help see frack interaction.
“You're not getting actual diagnostics from the well you're completing, but from that offset well,” Modeland said.
Recent advancements with flow-through cameras make it possible to image perforations in high-temperature locations, he said.
Danielle Fuselier, well construction director for North America Land at Baker Hughes, said the Haynesville presents similar challenges to drilling operations as it does to completions. As a result, drilling rates in the Haynesville have historically been slower than in other basins.
“We've gone from mile-a-day wells in Appalachia to now 2.5- to 3-mile-a-day wells. Here in the Haynesville, it's a good day if you can do a thousand feet,” she said.
Harsh Haynesville
One of the biggest challenges in the Haynesville involves technology that can survive the play’s harsh environment and deliver efficiencies common to other regions, Fuselier said.
Historically, the drill bit has been one of the limiters in drilling efficiency in the Haynesville, but advances in materials sciences, different geometries, non-planar shapes and flow that evacuates the cuttings all work to keep the cutting edge sharp and efficient, Fuselier said.
Drill bits have one of the fastest innovation cycles in drilling, she said, which has helped deliver some “phenomenal” gains in drilling. In the past, bits only lasted 2,000 ft to 3,000 ft when drilling the Haynesville’s intermediate section.
“We're doing 6,000 ft [intermediate section] runs with one bit,” Fuselier said. “From a technology standpoint, I'm pretty pumped about the future.”
Materials science has also helped with mud motors.
Temperatures of 340 F are “no longer that critical threshold, and as we've coupled that with new power section designs, the high temp is not necessarily what's holding us back in those spaces,” Fuselier said.
Advances in electronics have been a key enabler, she said.
“In terms of durable environment, we've come a long way. Electronics have become much smaller,” she said.
Baker Hughes has been developing high temperature capabilities, she said, and some early testing in Mexico and China generated promising results. She said Baker Hughes is in early stages of bringing some of that into the U.S. land market.
Under pressure
Completions in the Haynesville remain difficult, Modeland said.
“It's got probably the highest cost of completions just in the intensity of what we're doing. And then the pressure side, the horsepower requirement,” he said.
While the Haynesville has been home to some simul-fracs, they are not standard in that region like they are in the Permian where there’s tight well spacing, four- to six-well pads and shorter drill and completion cycle times, he said.
“You look at the Haynesville, the drill times and the completion times are a lot larger cycle time from capital spend to getting that return. Then the well spacing's wider. You might have a couple benches … but you don't have that massive amount of wells right there,” he said.
But he sees some opportunity with simul-frac and trimul-frac for the region.
“That would really be a next step game changer if we can get the logistics” sorted out for such operations, he said.
But one of the biggest opportunities in the Haynesville is refrac operations, he said. It helps, he added, that Haynesville has historically had some of the best performing refrac wells in North America.
“The cycle time on a new drill is so much longer than the cycle time on just relining an existing well with a liner and then doing a refrac,” Modeland said.
He believes drilling and completions across North America will continue to get deeper and exceed 400 F, but that the industry is innovative and creative enough to meet those challenges.
And the Haynesville Shale, where some of those technologies are being developed and finetuned, is “a good playground for helping out all the other areas as well,” he said.
Recommended Reading
Ithaca Energy to Buy Eni's UK Assets in $938MM North Sea Deal
2024-04-23 - Eni, one of Italy's biggest energy companies, will transfer its U.K. business in exchange for 38.5% of Ithaca's share capital, while the existing Ithaca Energy shareholders will own the remaining 61.5% of the combined group.
Triangle Energy, JV Set to Drill in North Perth Basin
2024-04-18 - The Booth-1 prospect is planned to be the first well in the joint venture’s —Triangle Energy, Strike Energy and New Zealand Oil and Gas — upcoming drilling campaign.
EIG’s MidOcean Closes Purchase of 20% Stake in Peru LNG
2024-04-23 - MidOcean Energy’s deal for SK Earthon’s Peru LNG follows a March deal to purchase Tokyo Gas’ LNG interests in Australia.
Equinor Acquires Stake in Standard Lithium Smackover Projects
2024-05-08 - Equinor’s transaction, completed effective May 7, includes interests in Standard Lithium’s flagship South West Arkansas Project and East Texas properties.
Crescent Point Divests Non-core Saskatchewan Assets to Saturn Oil & Gas
2024-05-07 - Crescent Point Energy is divesting non-core assets to boost its portfolio for long-term sustainability and repay debt.