The oil and gas industry routinely faces significant challenges and extreme conditions in the discovery of hydrocarbons because of geography, climate conditions or war. In dealing with these challenges, we normally think of employing seismic crews, engineers or drillers.
Although Geotrace’s Tigress software division was not exploring for oil and gas, it overcame all three of these obstacles recently in building databases of several large fields in Iraq by bringing in information analysts, interpreters and data managers.
Tigress, which stands for The Integrated Geoscience and Reservoir Engineering Software
![]() |
|
Map of the major oil fields in Iraq. (All images courtesy of Geotrace) |
The software takes an integrated real-time approach to data management. It assumes that a company’s database is a living organism and that it completely describes the company’s operation. In the early stages of an exploration company, data is often all it has to describe assets and confirm a company’s value.
The objective
The team was tasked with locating, preparing and quality-checking large volumes of disparate data for several large oil fields in Iraq determined to be worth billions of dollars.
Several challenges presented themselves in completing this project, including the uncertainty of working in the Iraqi environment and having to work under a tight timeframe of only 3 months to first interpretation.
The work conducted by the team was extremely valuable to the customer, who did not yet know the full value of the assets because so much of the data was disorganized and not able to be evaluated because of infrastructure damage and turmoil as a result of the ongoing war.
The uncertainties of Iraq
Following military intervention in Iraq, the new government found itself custodian to some of
![]() ![]() |
|
Figure 2. Integrated displays of geological and geophysical information. |
The team was surprised to learn how closely the data management situation in post-war Iraq mirrored the situation in many oil companies in stable political environments. Some data was lost and took time to locate or recreate. There was no central catalogue of the data available or its location. Some data were damaged and had to be repaired. Systems and procedures needed to be established. The data volumes were large, and new data was being located and added to the database every day.
Parameters of the project
At the outset of the project, it was decided that no allowances would be made for the highly political circumstances. That is, the database created would need to meet the same rigorous standards in terms of record-keeping and quality assurance applied at a “blue chip” oil company in a stable environment.
Additionally, it was determined that no concessions would be made in terms of both data security and access control.
Establishing exact standards at the outset of the project proved to be of critical importance. When setting up an E&P database from scratch, it is possible to compromise quality for speed. When up against a tight deadline, it always is tempting to focus on those areas that are of most importance in the short term. Although this does help achieve short-term deadlines, it is an unwise approach as these deadlines are soon eclipsed by more demanding information management considerations.
Execution of the project
This large amount of data needed to be located, catalogued and loaded for several fields simultaneously. Interpreters hungry for data wanted their workstations populated as soon as useful data became available.
The team controlled the project workflow while keeping records of receipt and delivery along the way. At the same time, the team built a catalogue of data and constantly updated it, indicating the data’s availability and condition.
Several weeks into the project, the scene was a living working data factory with new records
![]() |
|
Figure 3. Plot showing surface information from a typical integrated E&P database. |
The consultants running the project had always known that a real-time system similar to Tigress would be essential in managing a large and complicated project. However, they did not anticipate how challenging it would be to build a database in several locations around the country without a link to the Internet. The team was able to coordinate eight separate databases in real time.
Building E&P databases always is a collaborative effort. This is one of the reasons why using an integrated approach is critical. The Iraqi case study is an excellent example that demonstrates this. Conflict often disperses people geographically. In the case of the Iraq example, many of the experts were also members of the Iraqi Diaspora. The knowledge held by these individuals would be essential to accurate interpretations; however, some were not ready to return to their homeland. Others had left before the conflict and had established homes all over the world, particularly in Jordan, the United States and various European countries. To ensure success, it was important to involve these individuals at the early stages of the database build. Waiting until the interpretation stage would have diminished the quality of the project.
Integrated system importance
This unique project tested the benefits of an integrated system. In its original design, the software was conceived as an integrated system to bring together scientists or different disciplines to collaborate as part of an integrated asset team. In the case of the Iraqi case study, it was the integrated nature of both the data and the team which proved to yield some unexpected benefits.
Lessons learned
Data in an exploration and production database is in some form or fashion interrelated. What
![]() |
|
Figure 4. An integrated reservoir model. |
The use of an integrated approach meant that any consumer of the information produced in the Tigress database could see at a glance what had been done, by whom and, most importantly, how and why.
The project in the Iraqi oil field might have been the team’s most extreme data management challenge to date, but as often the case in such situations, it identified techniques, methods and possibilities that have extremely useful applications in somewhat more everyday operations.
Recommended Reading
Energy Transition in Motion (Week of Feb. 21, 2025)
2025-02-21 - Here is a look at some of this week’s renewable energy news, including a record for community solar capacity in the U.S.
Oxy’s Stratos Direct Air Capture Project Nears Finish Line
2025-02-20 - Stratos Phase 1 is 94% complete overall and 98% complete on construction, Occidental Petroleum says.
EDP Renewables Brings Mississippi Solar Park Online with Amazon as Buyer
2025-02-19 - The project marks EDP Renewables North America’s second utility-scale project in Mississippi.
GA Drilling Moves Deep Geothermal Tech Closer to Commercialization
2025-02-19 - The U.S. Department of Energy estimates the next generation of geothermal projects could provide some 90 gigawatts in the U.S. by 2050.
West Virginia Gains Authority for Class VI Wells for CCS
2025-02-18 - The state joins North Dakota, Wyoming and Louisiana in securing approval from the Environmental Protection Agency for Class VI well primacy for carbon capture and storage.