Presented by:
Editor's note: This article appears in the E&P newsletter. Subscribe here.
The increasing scrutiny on induced seismicity and the desire to reduce groundwater consumption has led to increasing rates of produced water recycling in the Permian Basin among E&P operators. However, once an operator has completed its development and no longer has a need for recycled volumes, the end result is produced water injection.
Historically, operators have been hesitant to share their own produced water infrastructure with other operators due to liability and timing challenges, but with the development of third-party water midstream infrastructure, produced water can continue to be recycled in areas of completed developments and moved via large-diameter pipe to areas with upcoming completions.
XRI, a water midstream operator in the Permian, has more than 350 miles of permanent, large-diameter pipeline infrastructure and an aggregated system capacity to run approximately 1.25 MMbbl/d so as to provide full-cycle water solutions to its E&P customers and saving 180 MMbbl of produced water from being injected annually.
In Midland County, XRI’s system consists of more than 50 miles of large-diameter pipelines serving the most active operators in the county. The system has evolved from supplying non-potable brackish groundwater to incorporating produced water takeaway and recycled water supply to meet the growing request for produced water utilization in completions.
Midland County case study
Operator A inquired XRI about the availability of treated produced water for its completions in an area where it did not previously utilize produced water. Approximately 20 miles away on XRI’s pipeline system, Operator B independently inquired XRI about taking away excess produced water with its completions activities located out of the area. Operator A’s volume needs allowed 100% utilization of the excess water as well as water in Operator B’s system that would have been injected.
However, Operator A’s completion schedule was not aligned when Operator B’s peak occurred. XRI was then able to utilize an interconnect with Operator C's pit to store’s Operator B excess volumes until Operator A’s completion started.
Operator C's stored pit volumes were used to end the completion to allow Operator B's produced water volumes to be prepared for another completion in the same manner. Peak rates for this project were in excess of 100,000 bbl/d, and in total 3.3 MMbbl of produced water was recycled as opposed to injection.
Recommended Reading
Venture Global LNG Files Paperwork for IPO
2024-12-20 - Venture Global LNG filed initial paperwork for an IPO on Dec. 20, about a week after the company’s Plaquemines LNG facility started production.
Dividends Declared Week of Dec. 16
2024-12-20 - As fourth-quarter 2024 nears its end, here is a compilation of dividends declared from select upstream, midstream and service and supply companies.
Rising Phoenix Names Executive as New Director of Capital
2024-12-19 - Rising Phoenix Capital appointed Ben Fujihara, a tenured financial executive, to oversee the company’s capital strategy, investor relations and business development.
Natron Energy Appoints New CEO
2024-12-17 - Sodium ion battery technology company Natron Energy has appointed Wendell Brooks as the company’s new CEO to lead growth initiatives in 2025.
NOV Appoints Former Denbury CEO Chris Kendall to Board
2024-12-16 - NOV Inc. appointed former Denbury CEO Chris Kendall to its board, which has expanded to 11 directors.
Comments
Add new comment
This conversation is moderated according to Hart Energy community rules. Please read the rules before joining the discussion. If you’re experiencing any technical problems, please contact our customer care team.