Glasgow-based Aggreko, provider of mobile, modular power, temperature control and energy services, announced on Jan. 25 that is has completed commissioning of the largest flare gas to power project in the Middle East to date at 165 MW capacity. The plant is situated nearby the Saqala Field, Garmain block in South East Kurdistan.
The 165 MW modular power plant has run at full capacity for 72 hours in the project’s final site acceptance test, marking successful on-time, on-budget delivery. The plant is run on approximately 40 million square cubic feet per day of associated petroleum gas from the Saqala Field, saving 840 tonnes of CO2 per day, and cutting flaring by a third, the company said in a press release.
Delivered over the course of 2020-2021 against the backdrop of the pandemic, the project was conceived and executed in close collaboration with Kurdistan’s Ministry of National Resources (MNR) and Ministry of Electricity (MOE). Aggreko also delivered a new 6km gathering pipeline to transport the APG to the power plant and upgraded 7km of 33 kV and 33km of 132 kV overhead cables to new high tensile low sage conductors in order for the local distribution grid to handle the new power plant’s full output.
Ahmed Mufti, Kurdistan Regional Government’s Deputy Minister of Natural Resources said, “We worked with Aggreko to provide a creative solution to convert flare gas to power in a way that directly benefits the local population and the region in general, while creating a positive environmental impact and improving air quality."
Phil Burns, Managing Director for Aggreko Middle East, comments: “Kurdistan’s Regional Government has been forward-thinking in looking for ways to capture and convert gas that would otherwise be flared, to unlock production and power the local economy. We are extremely proud to have worked with the Ministries to deliver the Middle East’s largest flare gas to power project to date, while upgrading the local infrastructure to the lasting benefit of the community and businesses it serves.”
The project is now contracted to run for four years. Built using 192 MW of modular gas generators, the plant can easily be scaled up or down in response to changing gas volumes. Approximately 60 Aggreko engineers have delivered the project, with 80 local jobs created directly and indirectly for the site's delivery and ongoing operation, including 44 locals who have already commenced Aggreko's official training scheme.
Recommended Reading
Record NGL Volumes Earn Targa $1.07B in Profits in 3Q
2024-11-06 - Targa Resources reported record NGL transportation and fractionation volumes in the Permian Basin, where associated natural gas production continues to rise.
BP Profit Falls On Weak Oil Prices, May Slow Share Buybacks
2024-10-30 - Despite a drop in profit due to weak oil prices, BP reported strong results from its U.S. shale segment and new momentum in the Gulf of Mexico.
Dividends Declared (Sept. 30 - Oct. 11, 2024)
2024-10-11 - Here is a compilation of dividends and distributions declared from select upstream, midstream and service and supply companies from Sept. 30 to Oct. 11.
BKV Prices IPO at $270MM Nearly Two Years After First Filing
2024-09-25 - BKV Corp. priced its common shares at $18 each after and will begin trading on Sept. 26, about two years after the Denver company first filed for an IPO.
Post Oak Backs New Permian Team, But PE Faces Uphill Fundraising Battle
2024-10-11 - As private equity begins the process of recycling inventory, likely to be divested from large-scale mergers, executives acknowledged that raising funds has become increasingly difficult.
Comments
Add new comment
This conversation is moderated according to Hart Energy community rules. Please read the rules before joining the discussion. If you’re experiencing any technical problems, please contact our customer care team.