Origin Energy has marked a major milestone in the development of its $24.7 billion Australia Pacific LNG project on Queensland’s Curtis Island, starting up the first of seven gas turbine power generators.
While the majority of the natural gas arriving at the LNG facility will be processed and exported as LNG, a small amount will be used to power the gas turbine generators to generate the electrical power required to operate the two LNG processing trains.
APLNG chief executive Page Maxson said the successful start-up of the first turbine followed on from the completion of the pipeline and first gas arriving at the LNG facility earlier this year.
“The complexity and scale of this accomplishment is significant and required the completion of key safety and operating systems,” he said.
“Over the coming months, we will progressively test and start additional critical elements of the processing trains to bring the LNG facility on line and be ready for first LNG export.”
Each of the seven gas turbine generators, constructed by Bechtel, will produce a peak output of approximately 15 megawatts and will deliver 105 MW combined.
Bechtel Gladstone general manager Kevin Berg said the Bechtel team was progressively completing the commissioning work on the remaining components of the first train and, in parallel, constructing and commissioning the second train.
The project is now heading into the final stages of the construction phase in preparation to deliver first LNG in mid-2015.
APLNG is a joint venture between Origin (37.5 per cent), ConocoPhillips (37.5 per cent) and Sinopec (25 per cent).
The first two gas production trains comprising APLNG will have the capacity to process up to 9 mtpa of gas.
Lauren Barrett can be reached at lbarrett@hartenergy.com
Recommended Reading
BP to Use Palantir Software to Improve AI in Operations
2024-09-09 - BP and Palantir have agreed to a five-year strategic relationship in which Palantir’s AIP software will use large language models to improve BP operations.
TGS Awarded 2D Survey in the Sumatra Basin
2024-09-09 - TGS’ Sumatra Basin seismic acquisition is expected to be completed by the end of 2024.
Technip Awarded FEED for BP’s UK Hydrogen Project
2024-08-27 - BP’s H2Teesside is expected to be one of the U.K.’s largest low-carbon hydrogen production facilities and fully integrated with carbon capture technology.
TGS Releases Illinois Basin Carbon Storage Assessment
2024-09-03 - TGS’ assessment is intended to help energy companies and environmental stakeholders make informed, data-driven decisions for carbon storage projects.
PPG’s Insulation Coating Offers Oil, Gas Asset Protection in High Heat
2024-08-21 - The PPG Pitt-Therm 909 spray-on insutlation coating can withstand high temperatures to promote safety and corrosion resistance.
Comments
Add new comment
This conversation is moderated according to Hart Energy community rules. Please read the rules before joining the discussion. If you’re experiencing any technical problems, please contact our customer care team.