Trans Mountain Corp. plans to begin line fill in March or May on its long-delayed Canadian oil pipeline expansion, depending on the diameter of pipe it uses and assuming no new problems, the Canadian government-owned company said in a filing on Jan. 3.
The company is awaiting a regulatory decision on its request for a construction change.
Line fill is a final step before the expanded Alberta-to-British Columbia pipeline begins service, providing crucial additional access for Canadian oil to refineries on the U.S. West Coast and in Asia.
The project will nearly triple the pipeline's shipments to 890,000 bbl/d.
Trans Mountain said the new schedules assume that it faces no delays caused by challenges drilling into hard rock, such as tool damage. Trans Mountain continues to target the end of the first quarter to begin shipping crude and is developing contingency plans to address any challenges to that schedule, a spokesperson said in an email.
Trans Mountain had asked the Canada Energy Regulator (CER) to allow it to install smaller-diameter pipe in a 1.4-mile (2.3 km) section of the oil pipeline's route after encountering challenging drilling conditions in a mountainous area between Hope and Chilliwack, British Columbia.
The CER denied the request on Dec. 5, later saying that the application did not adequately address concerns about pipeline integrity and the environment. Trans Mountain then asked the regulator to reverse that decision on Dec. 14, warning of a possibly "catastrophic" two-year delay and billions of dollars in losses.
The CER has not yet made a decision.
The pipeline can enter service within one month of mechanical completion, which precedes line fill, Trans Mountain said in the filing.
Canadian heavy oil prices strengthened as the filing suggested Trans Mountain and the regulator are working hard to resolve construction problems, a trader said.
In Trans Mountain's 33-page filing, it told the CER it had considered numerous alternatives before settling on the revised plan for which it is seeking approval.
The company said it has faced growing problems with water flow and abnormal wear on tools as it drills into hard rock.
Under the worst-case scenario for the plan currently approved by CER, the company's horizontal directional drilling approach could fail and require a fresh alternative that may delay the project by two years to 30 months, Trans Mountain said.
Prime Minister Justin Trudeau's Liberal government bought the project in 2018 to ensure the expansion went ahead, but costs have ballooned to CA$30.9 billion (US$23.14 billion), more than four times the original budget.
Recommended Reading
APA Corp. Sells $700MM in Non-core Permian, Eagle Ford Assets
2024-05-20 - APA Corp. and subsidiary Apache are selling more than $700 million in non-core assets in the Permian Basin and Eagle Ford Shale—part of a plan to reduce debt after a $4.5 billion acquisition of Callon Petroleum.
Multi-basin Mayhem: Conoco, Marathon Tout Eagle Ford, Bakken Runway
2024-05-31 - ConocoPhillips and Marathon Oil—which both trace their roots to the breakup of John D. Rockefeller’s Standard Oil Trust more than a century ago—are combining in a $22.5 billion deal.
Continental, Antero, Other E&Ps Make Strides in Ground Game A&D
2024-08-08 - Operators have been hard at work on ground game dealmaking from the Permian to Appalachia through the first half of the year, according to reports by Continental Resources, Antero Resources, HighPeak Energy and others.
CEO: FireBird II Prowls Western Midland Basin for M&A, Deep Exploration
2024-05-23 - After selling the first FireBird Energy to Diamondback for $1.6 billion, the FireBird II team is adding leases and scaling oil production in the western Midland Basin, CEO Travis Thompson said at Hart Energy’s SUPER DUG Conference & Expo.
Bob Simpson-led TXO Partners Buys Williston Basin Assets for Nearly $300MM
2024-06-25 - TXO Partners, an upstream MLP founded by XTO Energy executive Bob Simpson, is acquiring assets in the Williston Basin—a region the XTO team knew quite well.