The Trans Mountain oil pipeline expansion could be delayed by up to nine months if regulators do not approve a route deviation request, the Canadian government corporation building the project said in a regulatory filing on Sept. 11.
The CA$30.9 billion (US$22.76 billion) pipeline, which will ship an extra 590,000 bbl/d of oil sands crude to Canada's Pacific Coast, was meant to start operating in the first quarter of 2024 but is facing delays and extra costs due to a last-minute route dispute.
Trans Mountain Corp. (TMC) has asked the Canada Energy Regulator (CER) to change the approved route on a 1.3-km (0.8 mile) section just south of Kamloops, British Columbia, to avoid micro-tunneling construction that the crown corporation says is not feasible technically or economically.
But TMC's proposal to instead lay the pipeline through a different area nearby, using horizontal directional drilling and a conventional open trench, is opposed by the Stk'emlupsemc te Secwepemc Nation (SSN) First Nation, an indigenous group whose territory the pipeline crosses.
In a letter to the CER laying out the "worst-case" scenario, TMC said being forced to continue with building a micro-tunnel on that part of the route could delay pipeline completion until December 2024 and add an extra CA$86 million in cost.
The earliest the micro-tunnel could be completed is by April, the company said.
However, the SSN First Nation said the lands TMC is proposing to disturb as part of the route deviation hold "profound spiritual and cultural significance."
A regulatory hearing on the route deviation request will take place next week in Calgary.
The Canadian oil industry is eagerly anticipating the start-up of the pipeline, which will significantly increase Canada's ability to export crude to the West Coast of the United States and Asia.
But the expansion project has been dogged by years of delays and will cost more than quadruple its original budget. Liberal Prime Minister Justin Trudeau's government bought the pipeline from Kinder Morgan Inc. in 2018.
Recommended Reading
SM Energy Marries Wildcatting and Analytics in the Oil Patch
2025-04-01 - As E&P SM Energy explores in Texas and Utah, Herb Vogel’s approach is far from a Hail Mary.
BlackRock’s Fink Calls for Reliable US Power Grid—Now
2025-03-31 - “That starts with fixing the slow, broken permitting processes in the U.S. and Europe,” Larry Fink, the co-founder, chairman and CEO of $12 trillion investment-management firm BlackRock Inc., told shareholders March 31.
E&P Highlights: March 31, 2025
2025-03-31 - Here’s a roundup of the latest E&P headlines, from a big CNOOC discovery in the South China Sea to Shell’s development offshore Brazil.
US Drillers Cut Oil, Gas Rigs for First Time in Three Weeks
2025-03-28 - The oil and gas rig count fell by one to 592 in the week to March 28.
BP Earns Approval to Redevelop Oil Fields in Northern Iraq
2025-03-27 - The agreement with Iraq’s government is for an initial phase that includes oil and gas production of more than 3 Bboe, BP stated.
Comments
Add new comment
This conversation is moderated according to Hart Energy community rules. Please read the rules before joining the discussion. If you’re experiencing any technical problems, please contact our customer care team.