CNOOC Ltd. has brought onstream its Suizhong 36-1/Luda 5-2 project in the shallow waters of the Bohai Sea, the company said Feb. 5.
CNOOC’s operated Suizhong 36-1/Luda 5-2 oilfield secondary adjustment and development project is in water depths of about 30 m in Bohai Sea’s Liaodong Bay.
The main production facilities include two new central processing platforms and two new wellhead platforms. CNOOC plans 118 development wells, including 81 producers and 37 water injection wells. The project is expected to reach peak production of approximately 30,300 bbl/d in 2025.
CNOOC said this project represents the largest secondary development and adjustment project offshore China. The development relies on onshore power supply.
CNOOC Ltd. holds 100% interest in the project.
Recommended Reading
E&P Highlights: Oct. 28, 2024
2024-10-28 - Here’s a roundup of the latest E&P headlines, including a new field coming onstream and an oilfield service provider unveiling new technology.
E&P Highlights: Sept. 23, 2024
2024-09-23 - Here's a roundup of the latest E&P headlines, including Turkey receiving its first floating LNG platform and a partnership between SLB and Aramco.
E&P Highlights: Sept. 16, 2024
2024-09-16 - Here’s a roundup of the latest E&P headlines, with an update on Hurricane Francine and a major contract between Saipem and QatarEnergy.
E&P Highlights: Sept. 9, 2024
2024-09-09 - Here’s a roundup of the latest E&P headlines, with Talos Energy announcing a new discovery and Trillion Energy achieving gas production from a revitalized field.
E&P Highlights: Nov. 4, 2024
2024-11-05 - Here’s a roundup of the latest E&P headlines, including a major development in Brazil coming online and a large contract in Saudi Arabia.
Comments
Add new comment
This conversation is moderated according to Hart Energy community rules. Please read the rules before joining the discussion. If you’re experiencing any technical problems, please contact our customer care team.