
The judge ruled for Williams’ proposed seven crossings of Energy Transfer’s pipeline network in the parish. (Source: Shutterstock/ Williams Cos.)
A judge in Beauregard Parish, Louisiana on June 3 ruled in favor of Williams Cos. in the firm’s ongoing dispute with Energy Transfer (ETP)over Williams’ Louisiana Energy Gateway (LEG) pipeline right-of-way.
The judge ruled for Williams’ proposed seven crossings of Energy Transfer’s pipeline network in the parish.
“This court finds that the construction, operation and maintenance of LEG’s proposed pipeline would not interfere with nor affect adversely the rights of ETP’s existing pipeline servitudes in Beauregard Parish,” wrote District Judge C. Kerry Anderson in the ruling on June 3.
The overall legal process between the midstream companies involves three more court cases and a ruling from the Federal Energy Regulatory Commission (FERC).
In an e-mail sent to Hart Energy, Williams stated, “We are pleased with the ruling received from the 36th Judicial District Court of Beauregard Parish. … This is another positive step in advancing the critical energy infrastructure needed to meet Louisiana’s, and the nation’s, demand for affordable and reliable energy.”
Energy Transfer argued that Williams’ proposed plan would cause safety issues on its already existing network. Williams argued that Energy Transfer was attempting to interfere unfairly with the development of its project.
Laura Creekmur, Williams’ vice president for communications and corporate social responsibility, said that the company is now awaiting the rulings over disputed crossings in DeSoto and Sabine parishes, Louisiana while another trial in Vernon Parish, Louisiana is scheduled to start June 10.
Along with Williams, Energy Transfer has filed suit against DT Midstream (DTM) and Momentum Midstream over line crossings. An appeals judge in April ruled in favor of DTM in its case.
Energy Transfer has also sought a ruling from FERC over Williams’ planned LEG crossing at the Louisiana-Texas border, filing a protest in April, saying that the crossing should be considered a transmission line, which would require federal oversight, as opposed to a gathering system. Williams responded that the facility does not meet the requirements for transmission lines.
Williams has moved back the completion date for the LEG project from late 2024 to the second half of 2025 after finding alternative routes that don’t cross ET’s network as a precaution.
Recommended Reading
E&Ps Posting Big Dean Wells at Midland’s Martin-Howard Border
2025-04-13 - Diamondback Energy, SM Energy and Occidental Petroleum are adding Dean laterals to multi-well developments south of the Dean play’s hotspot in southern Dawson County, according to Texas Railroad Commission data.
Chicken or the Egg? Policy and Tech Needed to Enable Hydrogen Market
2025-04-13 - Hydrogen project developers ask themselves the famous ‘chicken or the egg’ conundrum as they lean on policy, incentives and technology to bridge cost gaps.
Nabors, Corva Expand Alliance to Boost AI-Driven Innovation at Rig Sites
2025-04-13 - Nabors Drilling Technologies and Corva AI will use the RigCloud platform to provide real-time insights to crews directly at drilling sites, the companies said.
USD Completes Final Asset Sale of Hardisty Terminal
2025-04-13 - USD Partners was obligated to sell the Hardisty Terminal, in Alberta, Canada, after entering a forbearance agreement with its lenders on June 21 2024.
ADNOC Explores $9B Acquisition of Aethon’s Haynesville Assets—Report
2025-04-11 - Abu Dhabi National Oil Co. (ADNOC) is evaluating an acquisition of natural gas assets from Aethon Energy Management valued at around $9 billion, Bloomberg reported April 11.
Comments
Add new comment
This conversation is moderated according to Hart Energy community rules. Please read the rules before joining the discussion. If you’re experiencing any technical problems, please contact our customer care team.