A judge in Beauregard Parish, Louisiana on June 3 ruled in favor of Williams Cos. in the firm’s ongoing dispute with Energy Transfer (ETP)over Williams’ Louisiana Energy Gateway (LEG) pipeline right-of-way.
The judge ruled for Williams’ proposed seven crossings of Energy Transfer’s pipeline network in the parish.
“This court finds that the construction, operation and maintenance of LEG’s proposed pipeline would not interfere with nor affect adversely the rights of ETP’s existing pipeline servitudes in Beauregard Parish,” wrote District Judge C. Kerry Anderson in the ruling on June 3.
The overall legal process between the midstream companies involves three more court cases and a ruling from the Federal Energy Regulatory Commission (FERC).
In an e-mail sent to Hart Energy, Williams stated, “We are pleased with the ruling received from the 36th Judicial District Court of Beauregard Parish. … This is another positive step in advancing the critical energy infrastructure needed to meet Louisiana’s, and the nation’s, demand for affordable and reliable energy.”
Energy Transfer argued that Williams’ proposed plan would cause safety issues on its already existing network. Williams argued that Energy Transfer was attempting to interfere unfairly with the development of its project.
Laura Creekmur, Williams’ vice president for communications and corporate social responsibility, said that the company is now awaiting the rulings over disputed crossings in DeSoto and Sabine parishes, Louisiana while another trial in Vernon Parish, Louisiana is scheduled to start June 10.
Along with Williams, Energy Transfer has filed suit against DT Midstream (DTM) and Momentum Midstream over line crossings. An appeals judge in April ruled in favor of DTM in its case.
Energy Transfer has also sought a ruling from FERC over Williams’ planned LEG crossing at the Louisiana-Texas border, filing a protest in April, saying that the crossing should be considered a transmission line, which would require federal oversight, as opposed to a gathering system. Williams responded that the facility does not meet the requirements for transmission lines.
Williams has moved back the completion date for the LEG project from late 2024 to the second half of 2025 after finding alternative routes that don’t cross ET’s network as a precaution.
Recommended Reading
Exxon Mobil Completes Purchase of FPSO Offshore Guyana
2024-12-19 - Exxon Mobil Corp. paid $535 million to SBM Offshore for the FPSO, which will operate the unit through 2033.
M&A Target Double Eagle Ups Midland Oil Output 114% YOY
2025-01-27 - Double Eagle IV ramped up oil and gas production to more than 120,000 boe/d in November 2024, Texas data shows. The E&P is one of the most attractive private equity-backed M&A targets left in the Permian Basin.
Minerals M&A to Heat Up in ‘25 with $4B Diamondback Sale–KeyBanc
2025-01-21 - KeyBanc analysts expect an “imminent” Diamondback Energy dropdown to Viper Energy and at least a couple of $500 million deals by public mineral and royalty companies in 2025, with Sitio Royalties a likely acquirer.
DNOW Closes Cash Acquisition of Water Service Company Trojan Rentals
2024-11-26 - DNOW Inc.’s acquisition of Trojan Rentals LLC is its third purchase aimed at providing a holistic water management solution to the market, the company said.
Hollub: Oxy Low Carbon Ventures Bolsters US Energy Independence
2024-11-18 - Occidental Petroleum is making a number of low-carbon moves in the Permian—a maneuver that will bolster the U.S.' energy independence, CEO Vicki Hollub told Hart Energy in an exclusive interview.
Comments
Add new comment
This conversation is moderated according to Hart Energy community rules. Please read the rules before joining the discussion. If you’re experiencing any technical problems, please contact our customer care team.