Consisting of 176 turbines and three offshore substations on a nearly 113,000-acre lease area off Virginia Beach, the 2.6-gigawatt (GW) CVOW is the largest offshore wind project being developed in the U.S. (Source: Shutterstock)
Dominion Energy is set to begin offshore construction of the $9.8 billion Coastal Virginia Offshore Wind (CVOW) farm in second-quarter 2024, having secured final federal approvals for the project.
The U.S. Bureau of Ocean Energy Management gave its final approval to the project’s construction and operations plan, Dominion said Jan. 30. The U.S. Army Corps of Engineers also issued a permit to allow for permitted impacts to U.S. waters, including the electric transmission line connecting energy generated offshore to the onshore electric grid.
Consisting of 176 turbines and three offshore substations on a nearly 113,000-acre lease area off Virginia Beach, the 2.6-gigawatt (GW) CVOW is the largest offshore wind project being developed in the U.S. When complete, the project is expected to provide enough power for about 660,000 homes. Developers expect to complete the project in 2026.
“Virginia is leading the way for offshore wind as we near the start of offshore construction for Coastal Virginia Offshore Wind,” said Dominion Energy’s CEO Bob Blue. “These regulatory approvals keep CVOW on time and on budget as we focus on our mission of providing customers with reliable, affordable and increasingly clean energy.”
The approvals came amid continued efforts to reach the Biden administration’s offshore wind capacity target of 30 GW by 2030.
American Clean Power Association’s Vice President for Offshore Wind Anne Reynolds called the approval a milestone toward America’s energy security and clean energy future.
“This project demonstrates what offshore wind development can deliver onshore by attracting new investments in communities, building domestic supply chains, and revitalizing domestic ports,” Reynolds said in a statement. “Additionally, CVOW will enhance the resilience and reliability of Virginia’s electric grid, ensuring a more secure and stable energy supply for residents and businesses while also improving local air quality.”
Other approved commercial-scale offshore wind farms include Vineyard Wind 1, South Fork Wind, Ocean Wind 1 and Revolution Wind.
Despite the approvals, challenging macroeconomic conditions such as inflation, supply chain difficulties and interest rates have caused developers to rethink original plans. Several developers canceled contracts and halted developments as they pursued better prices and rebid projects.
RELATED
Equinor, Ørsted Bid for Better Contract in NY Offshore Wind Auction
RWE Offshore Wind CEO on Plans to Spend, Build Big in US
Avangrid, CIP Deliver First Power from Vineyard Wind
BP, Equinor Terminate Empire Wind 2 Contract Offshore New York
Dominion Energy’s project is currently on track and on budget, the company said.
In November, Dominion said it was in the advanced stages of a process to find an equity partner for CVOW. Speaking during the company’s third-quarter 2023 earnings call, Blue said 92% of the project’s costs—excluding contingency of about $370 million—are fixed. At the time, unfixed costs amounted to about $750 million, including onshore electrical work, fuel for transport and installation, plus certain project oversight costs.
Dominion Energy is scheduled to release its fourth-quarter results Feb. 22.
Recommended Reading
US Oil, Gas Rig Count Unchanged This Week
2025-03-14 - The oil and gas rig count was steady at 592 in the week to March 14. Baker Hughes said that puts the total rig count down 37, or about 6% below this time last year.
Diversified, Partners to Supply Electricity to Data Centers
2025-03-10 - Diversified Energy Co., FuelCell Energy Inc. and TESIAC will create an acquisition and development company focused on delivering reliable, cost efficient net-zero power from natural gas and captured coal mine methane.
E&P Highlights: Jan. 21, 2025
2025-01-21 - Here’s a roundup of the latest E&P headlines, with Flowserve getting a contract from ADNOC and a couple of offshore oil and gas discoveries.
US Oil Rig Count Rises to Highest Since June
2025-04-04 - Baker Hughes said oil rigs rose by five to 489 this week, their highest since June, while gas rigs fell by seven, the most in a week since May 2023, to 96, their lowest since September.
Huddleston: Haynesville E&P Aethon Ready for LNG, AI and Even an IPO
2025-01-22 - Gordon Huddleston, president and partner of Aethon Energy, talks about well costs in the western Haynesville, prepping for LNG and AI power demand and the company’s readiness for an IPO— if the conditions are right.
Comments
Add new comment
This conversation is moderated according to Hart Energy community rules. Please read the rules before joining the discussion. If you’re experiencing any technical problems, please contact our customer care team.