Energy Transfer LP said on July 21 it plans to finish the final phase of its long-delayed Mariner East 2 NGL pipeline expansion in Pennsylvania in the third quarter despite calls by county commissioners to shut some operating parts of the system.
Earlier this week, Chester County Commissioners asked the Pennsylvania Public Utility Commission (PUC) to shut the operating Mariner East 1 and a 12-inch (30-cm) “workaround” pipe being used by the Mariner East 2 expansion, according to local media.
The county commissioners said several sinkholes have developed this year near the Mariner East 2 construction site in West Whiteland Township in southeastern Pennsylvania about 30 miles (48 km) west of Philadelphia.
Energy Transfer’s Sunoco Pipeline unit used an existing 12-inch pipe—the so-called “workaround” pipe—to allow the 20-inch Mariner East 2 to enter service in December 2018 after numerous delays related to sinkholes and drilling fluid spills slowed the project’s construction.
In regards to the Chester County request, a spokesperson at Energy Transfer said “there are no safety concerns regarding the ongoing operations of our active pipelines in this area, which have safely operated for years.”
Mariner East transports liquids from the Marcellus/Utica shale in western Pennsylvania to customers in the state and elsewhere, including international exports from Energy Transfer’s Marcus Hook complex near Philadelphia.
Sunoco started work on the $2.5 billion Mariner East expansion in February 2017 and planned to finish the 350-mile (563-km) pipeline in third-quarter 2017.
Mariner East 2 did not enter service until December 2018 due primarily to several work stoppages by state agencies.
Since May 2017, Pennsylvania has issued 122 notices of violation to Mariner East, mostly for drilling fluid spills, including two in June.
Recommended Reading
SLB Proves Direct Lithium Extraction Technology
2024-09-10 - SLB says its integrated technology solution produces lithium from brine faster than conventional methods while using less land, water and chemicals.
MVP Lithium Taps Evove to Commission DLE Plant in Canada
2024-11-15 - Midas Vantage Projects Lithium said the plant will be located in the Montney Formation in Canada and is considered a “promising new lithium resource.”
Exxon Mobil, LG Chem Ink Deal for Lithium Carbonate
2024-11-20 - As part of the nonbinding offtake agreement announced Nov. 20, Exxon will supply lithium from its planned project to LG Chem’s cathode plant in Clarksville, Tennessee.
Energy Transition in Motion (Week of Sept. 13, 2024)
2024-09-13 - Here is a look at some of this week’s renewable energy news, including an agreement between Exxon Mobil and Mitsubishi Corp. concerning ammonia from a planned hydrogen facility in Texas.
Energy Transition in Motion (Week of Oct. 25, 2024)
2024-10-25 - Here is a look at some of this week’s renewable energy news, including a U.S. Geological Survey-led study pointing to massive estimated lithium reserves in the Arkansas Smackover.
Comments
Add new comment
This conversation is moderated according to Hart Energy community rules. Please read the rules before joining the discussion. If you’re experiencing any technical problems, please contact our customer care team.