Equinor will increase its LNG production at the Askeladd field by 18 Bcm of gas and 2 MMcm of condensate, a company press release announced on Dec. 12.
Phase 1 of the project will bring the gas and condensate from Askeladd, a satellite field of the Snøhvit field in northern Norway, through the Hammerfest LNG (HLNG) plant on the island of Melkøya. The field was developed as a subsea tie-in to the Hammerfest and Snøhvit facilities, the company stated.
Startup was delayed until this year despite the project's completion in 2020 due to a fire at the Melkøya plant.
"The gas [from Askeladd] will help extend plateau production from Hammerfest LNG on Melkøya up to three years," Equinor vice president of operations and maintenance, Hammerfest LNG Thor Johan Haave commented in the release.
Hammerfest LNG delivers approximately 18.4 MMcm/d of gas during regular production, helping supply 6.5 million European households and accounting for 5% of all Norwegian gas exports.
The projected cost approximately NOK$4.55 billion, coming in on schedule and NOK$650 million below the original cost estimate.
"HLNG delivers significant volumes to customers in Europe, and the gas from the Barents Sea reinforces our position as a predictable and reliable gas supplier," Haave added. "Askeladd and other projects in the region will ensure further value creation and production from HLNG for decades."
Moving forward, Equinor will be adding two new wells in Askeladd West tied into exisiting infrastructure to further develop onshore compression and electrification through the company's Snøhvit Project.
Recommended Reading
Woodside Reports Record Q3 Production, Narrows Guidance for 2024
2024-10-17 - Australia’s Woodside Energy reported record production of 577,000 boe/d in the third quarter of 2024, an 18% increase due to the start of the Sangomar project offshore Senegal. The Aussie company has narrowed its production guidance for 2024 as a result.
Mexico Pacific Working with Financial Advisers to Secure Saguaro LNG I FID
2024-10-23 - Mexico Pacific is working with MUFG, Santander and JP Morgan to arrange the financing needed to support FID and the anchor phase of Saguaro Energía LNG.
Sheffield: E&Ps’ Capital Starvation Not All Bad, But M&A Needs Work
2024-10-04 - Bryan Sheffield, managing partner of Formentera Partners and founder of Parsley Energy, discussed E&P capital, M&A barriers and how longer laterals could spur a “growth mode” at Hart Energy’s Energy Capital Conference.
Investor Returns Keep Aethon IPO-ready
2024-10-08 - Haynesville producer Aethon Energy is focused on investor returns, additional bolt-on acquisitions and mainly staying “IPO ready,” the company’s Senior Vice President of Finance said Oct. 3 at Hart Energy’s Energy Capital Conference (ECC) in Dallas.
New Fortress Makes Headway on $2.7B Debt Refinancing
2024-11-26 - New Fortress Energy Inc. anticipates raising approximately $325 million in gross proceeds through the refinancing.
Comments
Add new comment
This conversation is moderated according to Hart Energy community rules. Please read the rules before joining the discussion. If you’re experiencing any technical problems, please contact our customer care team.