U.S. energy company Equitrans Midstream Corp. still expects to complete the $6.6 billion Mountain Valley natural gas pipeline from West Virginia to Virginia in the second half of 2023, the company said on Aug. 2.
That follows news on Aug. 1 that Democratic U.S. Senator Joe Manchin secured a commitment from President Joe Biden, Senate Majority Leader Chuck Schumer and House of Representatives Speaker Nancy Pelosi to allow the long-delayed Mountain Valley to be completed.
Manchin’s deal and the announcement boosted Equitrans shares over 10% to a three-month high of $8.72 on Aug. 2.
Mountain Valley—the only big gas pipe under construction in Appalachia—is one of several U.S. pipeline projects delayed by regulatory and legal fights with environmental and local groups. These fights stem from federal permit problems issued during President Donald Trump’s administration.
The project is key to unlocking more gas supplies from Appalachia, the nation's biggest shale gas basin.
Equitrans said in its earnings release that the Mountain Valley venture was “engaged in the permitting process with the relevant federal agencies for the outstanding permits required to complete the project.”
Several agencies still need to reissue permits, including the U.S. Federal Energy Regulatory Commission, the U.S. Fish and Wildlife Service (Biological Opinion), U.S. Army Corps of Engineers, U.S. Forest Service and Bureau of Land Management (Right-of-Way across Jefferson National Forest).
Many of those permits were vacated by the U.S. Court of Appeals for the Fourth Circuit—some more than once.
When Mountain Valley construction started in February 2018, Equitrans estimated the 303-mile (488-km), 2 Bcf/d project would cost about $3.5 billion and enter service by late 2018.
Equitrans has said the pipeline was “nearly 94% complete.”
Equitrans said it has a 48.1% ownership interest in Mountain Valley and will operate the pipeline.
Mountain Valley is owned by units of Equitrans, NextEra Energy Inc., Consolidated Edison Inc., AltaGas Ltd. and RGC Resources Inc.
Recommended Reading
CNOOC’s Bohai Bay Well Achieves High Yield
2024-07-11 - CNOOC’s Bozhong 19-6 Condensate Gas Field D1 well, the first ultra-deep well in China’s Bohai Bay, is currently producing approximately 6,300 boe/d.
E&P Highlights: June 24, 2024
2024-06-24 - Here’s a roundup of the latest E&P headlines, including TotalEnergies working with Nigeria to reach FID on the Ubeta gas field and Chevron signing production sharing contracts for two blocks offshore Equatorial Guinea.
SilverBow Makes Horseshoe Lateral in Austin Chalk
2024-05-01 - SilverBow Resources’ 8,900-foot lateral was drilled in Live Oak County at the intersection of South Texas’ oil and condensate phases. It's a first in the Chalk.
Norway’s DNO Discovers Gas Condensate in North Sea’s Cuvette
2024-06-19 - Cuvette is the second well in DNO’s 2024 North Sea exploration program.
E&P Highlights: July 10, 2024
2024-07-10 - Here’s a roundup of the latest E&P headlines including TotalEnergies exiting South Africa to focus on opportunities in Namibia.