Equitrans Midstream Corp. has updated the Pipeline and Hazardous Materials Safety Administration (PHMSA) on the root cause investigation and analysis related to the Rager Mountain Storage facility incident that took place last year, according to an Aug. 24 press release.
The incident, in which Rager well #2244 started leaking natural gas in November 2022, was caused by water- and oxygen-induced corrosion on the outside diameter of the top joint of the well, and the infiltration of organic and/or inorganic matter into the annulus, resulting in the well casing failing, according to the release.
Based on the results of an inventory verification test, the company’s initial gas loss estimate for well #2244 was approximately 1.29 Bcf. Following the root cause analysis, that number increased to 1.164 Bcf. The analysis indicates that approximately 1.037 Bcf was vented to the atmosphere, while the remaining 0.127 Bcf was diverted and contained within an underground formation.
It has been confirmed through extensive field and laboratory soil and water well testing that no gas migrated to nearby residential areas.
In an effort to mitigate this incident, the company says it has worked with a variety of third-party experts to ensure that all causes and/or contributors have been identified and addressed. The casing on well #2244 has been replaced, and the well has been plugged—whether this plugging will be permanent or temporary is to be determined at a later date.
Recommended Reading
Mobile Pipeline Maker Hexagon Agility Receives $11.2MM Order
2024-12-31 - Hexagon Agility says an oilfield service company is planning on converting its well-completion equipment fleet from diesel to natural gas.
Kinder Morgan to Build $1.7B Texas Pipeline to Serve LNG Sector
2025-01-22 - Kinder Morgan said the 216-mile project will originate in Katy, Texas, and move gas volumes to the Gulf Coast’s LNG and industrial corridor beginning in 2027.
FERC Closes Out ’24 with Rulings to Boost LNG Supply
2025-01-06 - A trio of Federal Energy Regulatory Commission authorizations in the latter half of December allowed new LNG trains to begin operations or boosted gas supplies to the facilities.
Glenfarne Signs on to Develop Alaska LNG Project
2025-01-09 - Glenfarne has signed a deal with a state-owned Alaskan corporation to develop a natural gas pipeline and facilities for export and utility purposes.
Kinder Morgan Reaches FID for $1.4B Mississippi NatGas Pipeline
2024-12-19 - Kinder Morgan plans to keep boosting its capacity to the Southeast and is moving forward with a 206-mile pipeline with an initial capacity of 1.5 Bcf/d.
Comments
Add new comment
This conversation is moderated according to Hart Energy community rules. Please read the rules before joining the discussion. If you’re experiencing any technical problems, please contact our customer care team.