Companies are teaming up to improve midstream infrastructure at both sides of the country. For starters, Florida Power & Light Co. selected Sabal Trail Transmission LLC—a joint venture (JV) between Spectra Energy Corp. and NextEra Energy Inc.—and NextEra’s wholly owned subsidiary, Florida Southeast Connection LLC, to build two natural gas pipelines and an interconnection hub serving the Sunshine state and Georgia.
The $3 billion system will include a 465-mile interstate natural gas pipeline from Transco’s Station 85 in Choctaw County, Alabama, and a new central Florida hub south of Orlando where it will interconnect with two existing pipelines. The system will be capable of transporting more than 1 billion cubic feet (Bcf) per day of gas to serve local distribution companies, industrial users and gas-fired power generators.
Florida Southeast will invest approximately $550 million to construct a separate pipeline from the new hub to Florida Power’s Martin Clean Energy Center in Indiantown, Florida. Initial capacity will be 400 million cubic feet (MMcf) per day.
Permitting is under way for both projects with construction expected to begin in 2016 and service to start in 2017.
To the north, MarkWest Utica EMG LLC announced an infrastructure expansion to support Utica and Marcellus producers.
The JV between MarkWest Energy Partners LP and The Energy & Minerals Group signed a letter of intent with Kinder Morgan Energy Partners LP for a 400 MMcf per day cryogenic processing complex and natural gas liquids pipeline with an initial capacity of 200,000 barrels (bbl.) per day.
The JV will construct the processing complex on Kinder Morgan’s existing 220-acre site in Tuscarawas County, Ohio, which can accommodate 1 Bcf per day of processing capacity, MarkWest announced. Its MarkWest Utica unit would anchor the first of two 200 MMcf per-day plants, which is planned to be in service by fourth-quarter 2014. A second plant is expected to begin operation shortly thereafter.
The complex will be operated by MarkWest Utica, owned on a 50/50 basis and will provide customers with additional residue gas outlets to Tennessee Gas Pipeline Co. LLC and Dominion Transmission Inc. Kinder Morgan will operate the new pipeline, which would be expandable to 400,000 bbl. per day with the addition of new pump stations, and own at least 75% of it. A fourth-quarter 2015 in-service date is anticipated for the project pending sufficient shipper commitments, permitting and related regulatory approvals.
Recommended Reading
ConocoPhillips Hits Permian, Eagle Ford Records as Marathon Closing Nears
2024-11-01 - ConocoPhillips anticipates closing its $17.1 billion acquisition of Marathon Oil before year-end, adding assets in the Eagle Ford, the Bakken and the Permian Basin.
Chevron Targets Up to $8B in Free Cash Flow Growth Next Year, CEO Says
2025-01-08 - The No. 2 U.S. oil producer expects results to benefit from the start of new or expanded oil production projects in Kazakhstan, U.S. shale and the offshore U.S. Gulf of Mexico.
Artificial Lift Firm Flowco Seeks ~$2B Valuation with IPO
2025-01-07 - U.S. artificial lift services provider Flowco Holdings is planning an IPO that could value the company at about $2 billion, according to regulatory filings.
BP Profit Falls On Weak Oil Prices, May Slow Share Buybacks
2024-10-30 - Despite a drop in profit due to weak oil prices, BP reported strong results from its U.S. shale segment and new momentum in the Gulf of Mexico.
EON Enters Funding Arrangement for Permian Well Completions
2024-12-02 - EON Resources, formerly HNR Acquisition, is securing funds to develop 45 wells on its 13,700 leasehold acres in Eddy County, New Mexico.
Comments
Add new comment
This conversation is moderated according to Hart Energy community rules. Please read the rules before joining the discussion. If you’re experiencing any technical problems, please contact our customer care team.