Malaysian national oil company (NOC) Petronas is nearing the completion of its first pioneering floating LNG (FLNG) unit, the PFLNG 1, facility, which is due onstream by year-end. At the same time the NOC’s second and larger unit—PFLNG 2—being done in partnership with Murphy Oil also is well underway in terms of its construction program.
PFLNG 1 (also known as PFLNG Satu) will be moored over the Kanowit gas field 180km offshore Sarawak, Malaysia, and has been designed to produce up to 1.2 million tonnes per annum (mtpa) of LNG as part of Phase 1 of the Kumang Cluster Development. Scheduled for commercial startup early in 2016, PFLNG 1 is both on time and on budget—an impressive achievement for a project that represents such a bold step forward in terms of offshore technology development for its owner.
PFLNG 2, meanwhile, is destined to be commissioned during 2018 and initially employed and centered on the deepwater Rotan gas field in Murphy-operated Block H, 130 km offshore Sabah, Malaysia. It also is planned to receive gas in later phases from at least four other satellites in the block—Alum, Bemban, Buluh and the recently revealed 5.7 Bcm (200 Bcf) Permai Field. Murphy holds a 56 per cent interest in Block H, with Petronas owning the remaining stake.
PFLNG 2 milestone
Petronas and Murphy recently ticked off a key milestone in the latter project’s progress with the official steel cutting taking place at the Samsung Heavy Industries (SHI) shipyard in Geoje Island, South Korea. SHI is responsible for the engineering, procurement, construction, installation and commissioning of the unit along with its consortium partners JGC Corp. and JGC (Malaysia) Sdn. Bhd.
The hull and topsides of the PFLNG 2, which has a design capacity of 1.5 mtpa, will weigh 152,000 tonnes in total. The facility, which will be operated by Petronas, is expected to achieve a 10-year peak gas rate of approximately 5.9 MMcm/d (207 MMcf/d) gross, according to partner Murphy.
In a prepared statement, Datuk Abdullah Karim, vice president and venture director of LNG domestic projects for Petronas Refinery and Petrochemical Corp., said the NOC’s decision in January 2014 to make its final investment decision on the PFLNG 2 project was made with “the expectation for PFLNG 2 to embark on a technology solution to monetize a wider range of stranded gas fields when it is commissioned in 2018.”
Dual strategy
The company’s strategy for both FLNG units is simple: to prove them initially on their first selected fields and then move them around to exploit other remote stranded gas fields in Malaysia’s domestic waters. Interestingly, it also has indicated it will consider potentially leasing the FLNG units to other companies to help them unlock their own stranded gas resources, and not only within its own waters.
Once onstream, the two FLNG plants will raise Malaysia’s total LNG production to an estimated 28.9 mtpa.
Much responsibility rests on the shoulders of the first unit, therefore, and Petronas has been heavily involved in essentially micromanaging the PFLNG 1 project so that it stays on schedule and on budget and has exemplary safety performance. In March the operator achieved 12 million man-hours without any lost time injury since the project kicked off exactly three years earlier at the Daewoo Shipbuilding & Marine Engineering (DSME) shipyard in Okpo, South Korea.
Decade-long process
When the 365-m-longfacility starts commercial production in first-quarter 2016, it will be the culmination of a process that started a decade earlier, when the FLNG concept was first seriously considered by Petronas.
After initial conceptual studies starting in 2006 confirmed the technical and economic viability of the proposed solution to Petronas, an engineering, procurement, construction, installation and commissioning contract for PFLNG 1 was eventually awarded to the DSME-Technip consortium in March 2012. The consortium partners had previously
carried out the FEED work on the facility after being awarded that contract in late 2010. Virtually all the engineering and procurement activities for the project have been done in Malaysia.
The facility consists of 22 modular systems including gas treatment, liquefaction, storage and offloading systems, with the liquefaction system to convert the gas to liquid at a temperature of -162 C (-260 F), which reduces the volume of the gas 600 times.
The FLNG vessel will be powered 100 MW of electricity using natural gas as the source and will weigh in at 132,000 tonnes in total. Petronas said it also has been careful to put in place a “more robust than usual” operational system so it will need less frequent maintenance than what is normally expected for an onshore plant—the company already has eight existing onshore LNG trains.
Other innovations have included the use of nitrogen as a refrigerant, which Technip said gives easier operability and which is a world-first for this capacity. DSME, for its part, also recognized that due to the large volume of work created by the PFLNG 1 project (as well as several other large offshore projects it was working on simultaneously), it was necessary to fabricate more topsides modules using subcontractors, including DSME’s own subsidiary yards.
Big sister
The unit’s big sister, PFLNG 2, will be sited on the Rotan Field offshore Sabah. Discovered in early 2007, this field lies in 1150 m of water and was the first find made in the block. Operator Murphy has since discovered seven fields within the permit, with Rotan itself estimated to hold recoverable reserves of around 26.9 Bcm of gas.
The nonpropelled unit will, like its smaller sister, be moored using an external turret and be designed to operate for 20 years without drydocking. JGC is looking after the engineering and procurement of the topside LNG facilities, with Air Products supplying its proprietary AP-NTM LNG process technology and associated equipment. In addition, GE Oil & Gas will supply two nitrogen trains incorporating a pair of aeroderivative gas turbines in mechanical drive mode to cool the gas to a liquid state as well as four gas turbine generator systems.
SHI, which is constructing the hull and modular facilities, said that the keel-laying ceremony for the vessel at its Geoje yard is currently on schedule for this December. The hull is expected to be launched in April 2016, and integration works are planned to get underway by July 2016. The American Bureau of Shipping will be providing classification and statutory certification services for the vessel.
Industry interest
According to Adnan Zainal Abidin, Petronas’ vice president of global upstream LNG projects, even though the first facility has not yet left the dock, it has been attracting inquiries from multinational companies about the possibility of chartering it.
But the first priority, he said, is to prove the technology successful by monetizing the gas from the Kanowit and Rotan fields before embarking on any other commercial ventures. “Our priority is to prove our worth, and hopefully this will open doors for us. We have already been approached by multinational companies to use our floaters for one of their fields, but for us the focus is to get this out of the shipyard and have it commissioned and run successfully.
“Once we’ve done this, we can show the world this thing is happening,” he added. “I have no doubt in my mind this will lead to other commercial opportunities beyond Malaysia.”
Recommended Reading
Reuters: Northern Oil and Gas in Bid to Acquire Smaller Rival Granite Ridge, Sources Say
2024-12-20 - Northern Oil and Gas has made an acquisition offer for Granite Ridge Resources, according to people familiar with the matter.
STEP Energy Services Drops Go-Private Deal as Shareholders Balk
2024-12-20 - STEP Energy Services has terminated its agreement with ARC Energy Fund 8 to go private in an all-cash transaction for CA$5 per share.
Allete Gets OK From FERC for $6.2B Sale to Canada Pension Plan, GIP
2024-12-20 - Allete Inc. announced its acquisition by the Canada Pension Plan Investment Board and Global Infrastructure Partners in May.
LandBridge Closes Deal for 46,000 Surface Acres in Delaware Basin
2024-12-20 - LandBridge Co., which held a successful IPO in August, added about 53,000 acres and now holds about 273,000 acres.
Battalion Oil Walks Away from Fury Resources Buyout
2024-12-20 - The Battalion Oil-Fury Resources merger had been in discussions for more than a year, but Battalion said Fury failed to meet financial deadlines to continue the talks.
Comments
Add new comment
This conversation is moderated according to Hart Energy community rules. Please read the rules before joining the discussion. If you’re experiencing any technical problems, please contact our customer care team.