Sarawak Energy aims to install at least 400 megawatts (MW) of floating solar power capacity at its dams by 2030 as the Malaysian utility expands to meet rising demand for renewables from neighboring countries, its group chief executive said.
The company owned by the Malaysian state of Sarawak, which produces most of its power from hydroelectric dams, is expanding into solar capacity as it seeks to reduce reliance on coal and ramp up exports to neighboring Sabah state, and countries such as Indonesia, Brunei and Singapore.
Sarawak Energy started construction at its first 50 MW floating solar unit at its Batang Ai dam this month which is expected to be completed by end-2024, CEO Sharbini Suhaili told Reuters on June 27 on the sidelines of an Energy Asia conference.
He said studies found that the company could reliably connect up to 1,500 MW across its three hydropower plants to its grid. Sarawak Energy is also building a fourth hydropower plant to be commissioned by 2028, which will bring its total hydropower capacity to 4,737 MW.
The company has signed agreements to export 30 MW to 50 MW of electricity to Sabah state in 2024.
Sarawak Energy exports about 80 MW to 100 MW of electricity to Indonesia's West Kalimantan and is building a 1,375 MW hydropower plant with its partner in North Kalimantan which may come online by 2030, Sharbini said.
Sarawak Energy is also in discussions with Brunei as well as Singapore, where it has completed a feasibility study to export hydropower via undersea cables around 2030, but the high cost and technical difficulties remain a challenge.
"About 70-80% of the cable will be in Indonesian waters, so that we need to manage as well," he said.
Such a connection would help kickstart an ASEAN power grid, Sharbini said, an idea that has been long-discussed but has remained on the drawing board.
Sarawak Energy plans to reduce the share of coal in its power mix to 10% by 2030 from the current 18%, Sharbini said, in part by decommissioning its 210 MW Sejingkat power plant by 2028 and the 270 MW Mukah power plant after 2030, he said.
Its 624 MW Balingian coal power plant, built in 2020, will be retained to ensure energy security, he said.
Recommended Reading
Martin Midstream Terminates Merger Agreement Following Pushback
2024-12-27 - Martin Midstream Partners will continue operating as a standalone publicly traded company following termination of its deal to merge with Martin Resource Management Corp.
NOG: Company Not in ‘Formal Negotiations’ to Buy Granite Ridge
2024-12-23 - Northern Oil and Gas, responding to media reports that it has made two offers for Granite Ridge Resources, said it’s not engage in formal negotiations to buy the company.
Reuters: Northern Oil and Gas in Bid to Acquire Smaller Rival Granite Ridge, Sources Say
2024-12-20 - Northern Oil and Gas has made an acquisition offer for Granite Ridge Resources, according to people familiar with the matter.
STEP Energy Services Drops Go-Private Deal as Shareholders Balk
2024-12-20 - STEP Energy Services has terminated its agreement with ARC Energy Fund 8 to go private in an all-cash transaction for CA$5 per share.
Allete Gets OK From FERC for $6.2B Sale to Canada Pension Plan, GIP
2024-12-20 - Allete Inc. announced its acquisition by the Canada Pension Plan Investment Board and Global Infrastructure Partners in May.
Comments
Add new comment
This conversation is moderated according to Hart Energy community rules. Please read the rules before joining the discussion. If you’re experiencing any technical problems, please contact our customer care team.