WBI Energy Inc., a subsidiary of MDU Resources Group Inc., put the North Bakken Expansion project into service on Feb. 1 after completing construction and testing on the natural gas pipeline.
The expansion has capacity to transport 250 million cubic feet of natural gas per day from the Bakken production area in North Dakota, with the potential to be increased up to 625 million cubic feet per day through additional compression if needed to meet growing customer demand.
As part of the project, WBI Energy and its main contractor, Michels Corp., completed a 15,426-foot horizontal directional drill of a 24-inch pipeline crossing Lake Sakakawea on the Missouri River in North Dakota. The crossing of just less than 3 miles is one of the longest of its kind.
"We are excited to put this project into service and help producers move more natural gas to market while reducing flaring in the Bakken region," David L. Goodin, president and CEO of MDU Resources, said. "With this project, WBI Energy's total pipeline system capacity is more than 2.4 billion cubic feet of natural gas per day, and its strategic location within the Bakken provides further opportunities to continue expanding to serve projected production growth. We appreciate the ongoing support from federal, state and local officials for these types of projects and the economic and environmental benefits they provide."
WBI Energy and its contractors completed the North Bakken Expansion project under a shortened timeframe, reducing the original construction schedule by two months, after a delay in receiving approval from the Federal Energy Regulatory Commission to proceed.
The North Bakken Expansion project included construction of approximately 100 miles of natural gas pipeline, a compressor station expansion, a new compressor station and additional associated infrastructure in northwestern North Dakota.
Recommended Reading
Venture Global LNG Files Paperwork for IPO
2024-12-20 - Venture Global LNG filed initial paperwork for an IPO on Dec. 20, about a week after the company’s Plaquemines LNG facility started production.
Dividends Declared Week of Dec. 16
2024-12-20 - As fourth-quarter 2024 nears its end, here is a compilation of dividends declared from select upstream, midstream and service and supply companies.
Rising Phoenix Names Executive as New Director of Capital
2024-12-19 - Rising Phoenix Capital appointed Ben Fujihara, a tenured financial executive, to oversee the company’s capital strategy, investor relations and business development.
Natron Energy Appoints New CEO
2024-12-17 - Sodium ion battery technology company Natron Energy has appointed Wendell Brooks as the company’s new CEO to lead growth initiatives in 2025.
NOV Appoints Former Denbury CEO Chris Kendall to Board
2024-12-16 - NOV Inc. appointed former Denbury CEO Chris Kendall to its board, which has expanded to 11 directors.
Comments
Add new comment
This conversation is moderated according to Hart Energy community rules. Please read the rules before joining the discussion. If you’re experiencing any technical problems, please contact our customer care team.