Virginia natural gas company RGC Resources Inc.’s CEO said on Feb. 12 that the joint venture building the $5.8 billion-$6 billion Mountain Valley gas pipeline from West Virginia to Virginia expects to complete the project by the end of 2021.
That matches what other companies involved in the project have said since they decided in January to give up on a nationwide permit that covers all stream crossings and instead seek individual permits to cross the remaining roughly 430 streams.
“MVP (Mountain Valley Pipeline) believes that pursuing the individual permit process ... is the most efficient regulatory path to completing the remaining components of the project,” RGC CEO Paul Nester told analysts on a call.

Many analysts have said the Mountain Valley Pipeline was right to give up on the nationwide permit, which they said was facing serious environmental court challenges, but noted the pipeline will likely not enter service until 2022 because it will take considerable time to receive the remaining stream crossing and other permits.
The Mountain Valley Pipeline is one of several oil and gas pipelines delayed in recent years by regulatory and legal fights with states and environmental groups that found problems with permits issued by the Trump administration.
When construction started in February 2018, the Mountain Valley Pipeline was expected to cost about $3.5 billion and be completed by the end of 2018.
In answer to questions about whether President Joe Biden’s administration could stop the Mountain Valley Pipeline in a way similar to what it did to TC Energy’s Keystone XL oil pipeline, Nester said, “We don't believe that the current administration has the legal standing to stop the project.”
Nestor noted the 303-mile (488-km) project was “roughly 92% complete” with “more than 264 miles of pipe welded and in place.”
The Mountain Valley Pipeline is owned by units of Equitrans Midstream, NextEra Energy, Consolidated Edison, AltaGas and RGC.
Recommended Reading
Shale Outlook Appalachia: Natural Gas Poised to Pay
2025-01-09 - Increasing gas demand is expected to rally prices and boost midstream planning as a new Trump administration pledges to loosen permitting—setting the stage for M&A in the Appalachian Basin.
More Uinta, Green River Gas Needed as Western US Demand Grows
2025-01-22 - Natural gas demand in the western U.S. market is rising, risking supply shortages later this decade. Experts say gas from the Uinta and Green River basins will make up some of the shortfall.
Shale Outlook Permian: The Once and Future King Keeps Delivering
2025-01-11 - The Permian Basin’s core is in full-scale manufacturing mode, with smaller intrepid operators pushing the basin’s boundaries further and deeper.
Major Interest: Chevron, Shell Join Vaca Muerta Crude Pipe Project
2025-01-20 - Oil producers are pumping record levels from Argentina’s Vaca Muerta shale. Chevron and Shell have backed a new crude pipeline project that aims to boost takeaway capacity—and exports—of Vaca Muerta oil.
Back to the Future: US Shale is Growing Up
2025-01-07 - The Patch’s maturity will be tested in 2025 amid ongoing consolidation and geopolitical dissonance.
Comments
Add new comment
This conversation is moderated according to Hart Energy community rules. Please read the rules before joining the discussion. If you’re experiencing any technical problems, please contact our customer care team.