The U.S. Rockies oil and gas producing region stretches over five Western states: Colorado, Wyoming, Utah, Arizona and New Mexico. In 2008, the estimated ultimate recovery of total gas reserves in the Rockies was 374 trillion cubic feet, excluding coalbed methane, according to Colorado School of Mines’ Potential Gas Committee (PGC). The greatest potential for non-associated natural gas in the Rocky Mountain region is concentrated in southwest and south-central Wyoming, northwest Colorado and northeast Utah, and includes the Uinta, Piceance and Greater Green River basins.
Beginnings
Moving Rockies gas to market began in 1928, when Colorado Interstate Gas Co. began gas pipeline service to the Denver/Front Range markets. The 300-mile pipeline provided service from the Texas Panhandle to industrial markets. A residential gas market soon followed. Within five years, gas use in the Denver area more than tripled, as gas was increasingly used in homes for cooking and, later, for heating.
In the 1930s, El Paso Natural Gas pipeline was built to route gas volumes from the Texas and Oklahoma panhandles and the Permian Basin of Texas and New Mexico to markets in Arizona. About 10 years later, more infrastructure was built to reach California markets. Mountain Fuel Supply Co., a Questar Corp. predecessor, also began aggregating and routing this gas, to markets near Salt Lake City.
For many years, U.S. gas pipeline companies operated as regulated aggregators and merchants of the gas commodity. They built gathering and pipeline infrastructure from the wellhead out. All gas supply was treated as pipeline-system supply, and dedications of gas supplies and long-term contracts were the norm. All gas supply and sale prices were regulated.
Early regional pipelines developed in this era were, by their current names, Questar Pipeline, Kinder Morgan Interstate Pipeline, Northwest Pipeline, Williston Basin Interstate Pipeline, Southern Star Central Pipeline, and an expanded Colorado Interstate Gas Pipeline. Some were connected to and sourcing local markets only, while others were anchoring parties for what would later become the nucleus of a significant supply-region export capability. Due to the seasonal character of regional markets, and a lack of abundant gas-storage resource in the West, this regional export capability was a prerequisite for long-term supply development.
In the 1980s, gas-supply development in the Rockies continued to exceed local demand. With a growing national demand for gas and a shortage of developable gas supplies elsewhere, six pipeline companies created what would later be referred to as the Trailblazer Pipeline System, an integrated network of jointly owned feeder pipelines that provided access to developing supplies based upon each owner’s percent of ownership, pipeline capacity, shared costs and long-term reserves. Thus, Overthrust Pipeline, Wyoming Interstate Pipeline Co. (WIC) and the Trailblazer Pipeline were added to supply-aggregation and regional-export capability. The group provided additional west-to-east transportation capability, but the primary focus was adding half a billion cubic feet per day (Bcf/d) of export capability to the region.
In 1986, the Federal Energy Regulatory Commission issued Order 436 and a series of subsequent orders, which led to the eventual unbundling of the historical interstate gas-pipeline merchant functions, so Trailblazer was one of the last merchant systems built in the Rockies region.
In the 1990s, the Rockies’ take-away capacity reached 2 Bcf/d. The midstream industry continued to evolve as various companies took on roles in the unbundled world. In 1992, the Kern River Pipeline system was built from Opal, Wyoming, to Kern County, California. Several of the system’s anchor shippers were producers who chose to transport Rockies gas to support their enhanced-oil-recovery (EOR) efforts in the Kern County oilfields. The original Kern River system had 0.7 Bcf/d of capacity. However, not all of the gas went to EOR recovery efforts. Some shippers sent the gas to residential and industrial customers in Nevada and California.
As demand for Rockies gas continued to grow, additional take-away capacity was needed. New and expanded pipeline systems included the Pony Express oil pipeline conversion (1997, 0.24 Bcf/d), TransColorado Pipeline (1999, ultimately expanded to 0.6 Bcf/d), Trailblazer Pipeline expansion (2002, 0.33 Bcf/d), Kern River mainline expansion (2003, expanded by 0.9 Bcf/d), Cheyenne Plains Pipeline (2006, added 0.74 Bcf/d ), Grasslands Pipeline (0.23 Bcf/d) and the Rockies Express Pipeline (2009, 1.8 Bcf/d).
Over the years, Kern River has expanded several times, adding some 0.5 Bcf/d of capacity. Bison Pipeline is currently under construction and will add 0.5 Bcf/d of takeaway. When completed, the Ruby Pipeline will provide an additional 1.25 Bcf/d of capacity when it enters service in early 2011. These projects and others, as well as numerous internal expansions of existing systems, have or will provide more than 8 Bcf/d of additional regional export capability.
Mountain of Change
Today, as one looks at the Rockies region, there are marked differences from those early days. First, regional markets are generally consuming gas produced locally. Major market centers are Colorado’s Front Range and the Salt Lake City area.
Also, an integrated network of pipeline infrastructure now exists to collect and aggregate significant regional gas volumes and to export up to 10.5 Bcf/d of excess supply to markets in the Pacific Northwest, West, Southwest, Midcontinent and, more recently, the eastern U.S.
Facilities built within the region are significantly more integrated than in the past, and volumes flow northwest, west-to-east, east-to-west, and south. Many regional capacity constraints have been reduced or eliminated. With an expected leveling of recent production growth, this historically capacity-short region can meet anticipated need.
In fact, interruptible gas flows will finally begin to enter the regional gas transportation mix and regional trading hubs and related activities are expected to be greatly enhanced as flexibility finally starts to replace decades of constraint. With fewer internal-capacity constraints, and sufficient regional-export capacity, gas prices in the region should become more stable and more predictable. This stability will provide more certainty in ongoing and future supply-development planning and investment decisions.
The bottom line: One of the nation’s largest gas-supply regions has developed in the Rockies, and major pipeline infrastructure has followed suit. An analysis of each of the producing areas and details of related midstream infrastructure, including west-to-east, beginning in western Wyoming; southward into Colorado and New Mexico; and east-to-west, ending in Utah, illustrates the importance of the region’s energy-supply capability.
Overthrust Area/WY Thrust Belt
The site of one of the older supply developments in the Rockies, the Overthrust area consists of supply infrastructure in southwestern Wyoming and northeastern Utah. Conventional resource development in the area continues, and there is some limited coalbed-methane development activity. Gas in this area is generally routed to the Questar Pipeline, into the Overthrust Pipeline, or to Kern River Pipeline. The U.S. Geological Survey estimates that resources able to be developed in this area are about 1 trillion cubic feet.
Gathering Systems/Plants | Owner/Operator | Capacity | Commercial Role |
Painter gas plant | BP | 0.24 Bcf/d | Process gas for NGLs, fractionator, as well as remove nitrogen. Delivery: Kern River |
Anschutz East gas plant | Anschutz unit holders/BP | 0.34 Bcf/d | Process gas for NGLs, fractionator, as well as remove nitrogen. Delivery: Kern River |
Carter Creek plant Carter Creek compression | Chevron Columbia Gulf | 0.17 Bcf/d 0.12 Bcf/d | Process sour gas to remove H2S. Delivery: WIC |
Regional Exit Pipelines | Owner/Operator | Capacity | Commercial Role |
Questar Pipeline | Questar | 0.5 Bcf/d | Overthrust receipts |
Overthrust Pipeline | Questar | 0.5 Bcf/d | Overthrust receipts for eastbound flow to WIC |
Kern River Pipeline Painter lateral/compressor | MidAm Holdings | 0.26 Bcf/d | Delivery to markets in southwest & California and/or northbound to Opal |
Greater Green River/Jonah-Pinedale/Vicinity of Opal, Wyoming (West)
The western portion of the Greater Green River area provides significant resource potential, estimated at 53- to 82 trillion cubic feet of resource potential. The Opal Hub in Wyoming has become a regional market-trading hub, with numerous pipelines interconnecting there and large gas-processing plants in the Opal area.
Several major gas-gathering systems terminate into these processing plants. These include the Jonah gas-gathering system (capacity about 2 Bcf/d), gathering systems upstream of Williams’ Opal plant, and the Rendezvous Pipeline and gathering system.
Also, Williams’ Northwest Pipeline provides a limited wet-gas gathering capability into the Opal plant. Williams’ Opal plant has a processing capacity of 1.45 Bcf/d, and Enterprise Products’ Pioneer plant can process up to 0.75 Bcf/d.
Western Gas Resources’ Granger complex in the area can handle 0.35 Bcf/d. Recent Rockies pipeline expansions, altered connectivity and reconfigurations of Overthrust, Wyoming Interstate and Colorado Interstate, Questar, and other pipelines provide an additional 1.5 Bcf/d of supplies coming into the greater Opal trading area to compete for market share and export capacity—both eastbound and westbound. They also provide ultimate sourcing capability to the Ruby Pipeline. Most of this pipeline-transported gas has been treated or processed and is ready to compete for capacity on take-away pipelines.
Gathering Systems/Plants | Owner/Operator | Capacity | Commercial Role |
Jonah Gas Gathering Pioneer Gas Plant | Enterprise Products | 2.0 Bcf/d 1.25 Bcf/de | Green River receipts/Process Green River receipts Delivery: Overthrust Pipeline, WIC, Kern River |
Opal Gas Gathering (multiple systems) Opal Gas Plant | Williams Partners | 1.0 Bcf/d 1.45 Bcf/d | Green River receipts, Process/blend Delivery: Overthrust Pipeline, Kern, NWP, CIG, Ruby |
Rendezvous Gas Gathering | QEP Field Services | 0.45 Bcf/d | Feed processing plants |
Granger Area Gathering Granger Plant Complex Lincoln Rd. Plant | Various/Western Gas Resources | 0.8 Bcf/d 0.345 Bcf/d | Green River receipts/Process Green River receipts, fractionator Delivery: NWP, CIG, OT, Kern River, Questar |
QEP Gas Gathering Black Forks Plant Black Forks II (Q4 2011) | QEP Resources | 0.75 Bcf/d 0.31 Bcf/d 0.42 Bcf/d | Green River receipts/Process Green River receipts Delivery: NWP, RGS, OTP, Overland Trail |
Regional Exit Pipelines | Owner/Operator | Capacity | Commercial Role |
Kern River Gas Transmission | Mid-American Energy Holdings | 1.8 Bcf/d | Delivery to southwest and western markets |
Northwest Pipeline | Williams/Williams Partners | 0.6 Bcf/d 0.25 Bcf/d | West/Northbound on NWP to Pacific NW markets Southbound on NWP to Blanco Hub |
Overland Trail Pipeline | DCP Midstream | 0.15 Bcf/d | Delivery to Kern River |
Colorado Interstate | El Paso | 0.15 Bcf/d | Eastbound deliveries on CIG |
Overthrust Pipeline (Loop/2011) | Questar Pipeline | 0.8 Bcf/d 0.1 Bcf/d | (0.55 westbound capacity for WIC/Ruby shippers) Eastbound capacity |
Overthrust Pipeline (East to REX) | Questar Pipeline | 1.0 Bcf/d | Eastbound deliveries to REX pipeline |
Rendezvous Pipeline | Questar Pipeline | 0.33 Bcf/d | Black Forks and Granger plant to Kern River |
Ruby Pipeline (Spring 2011) | El Paso/Global Infrastructure Partners | 1.25 Bcf/d | Delivery to northern Nevada/California markets |
Greater Green River/Wamsutter, Wyoming (East)
The eastern portion of the Green River Basin has significant resource potential. Gas from this region generally flows east toward the Cheyenne Hub and traditional Rockies markets, and some is routed into the Rockies Express Pipeline toward eastern markets. Wamsutter, Wyoming, has become an interconnection point for several of the regional pipeline systems, where gas volumes are aggregated from the Greater Green River area, points west and the Piceance Basin. If transportation capacity eastward from the Wamsutter is limited, parties can transport volumes westward on other area pipelines and market their gas at Opal.
This flexibility and bi-directional flow capability is new to the Rockies region and is a welcome addition for upstream producers and other market participants. Flexibility will become increasingly important with the completion of the Ruby Pipeline and Kern River Apex expansions in 2011, which will add 1.5 Bcf/d of aggregated regional pipeline export capability. Gas from the Piceance Basin, gathered by the Rockies Express, flows to and through the Wamsutter area, where it is combined with receipts from the Green River area and other points west.
Gathering Systems/Plants | Owner/Operator | Capacity | Commercial Role |
Wamsutter Gathering Echo Springs Plant | Williams Partners | 0.4 Bcf/d 0.74 Bcf/d | Feed processing plant Process/treat, NGL disposition |
WGR Gathering (Table Rock, Wamsutter, Desert Springs) | Western Gas Resources | 0.1 Bcf/d | Gather area volumes |
Patrick Draw Plant | Western Gas Resources | 0.15 Bcf/d | Process/treat, NGL disposition |
Emigrant Trail Plant | QEP Field Services | 0.06 Bcf/d | Process/treat, NGL disposition |
Regional Exit Pipelines | Owner/Operator | Capacity | Commercial Role |
Wyoming Interstate Expansion | El Paso | 0.55 Bcf/d | REX lease capacity |
Wyoming Interstate Expansion | El Paso | 0.45 Bcf/d | WIC expansion services |
Wyoming Interstate Mainline | El Paso | 0.6 Bcf/d | WIC mainline capacity |
Overthrust Pipeline (Loop/2011) | Questar | 0.8 Bcf/d 0.1 Bcf/d | (0.55 Westbound capacity for WIC/Ruby shippers) Eastbound capacity |
Overthrust Pipeline (East to REX) | Questar | 1.0 Bcf/d | Eastbound deliveries to REX pipeline |
Colorado Interstate Mainline | El Paso | 0.6 Bcf/d | Delivery to downstream markets/Cheyenne Hub |
Southern Star Central | Southern Star | 0.195 Bcf/d | Delivery to downstream markets in Kansas |
Questar Pipeline | Questar | 0.3 Bcf/d | Direct supply attachment |
Wind River/Big Horn/Powder River
The Big Horn area (0.2- to 0.55 trillion cubic feet of resource potential) is sourced primarily from historical conventional resources, while the Wind River (0.9- to 1.94 trillion cubic feet) and Powder River Basins (8.8- to 15.5 trillion cubic feet) are also sourced from coalbed methane wells. The Powder River wells are very shallow and low pressure.
After an initial production surge, these wells produce for many years. The coalbed methane requires treating for CO2 and may require management of significant amounts of water produced along with the gas stream.
Gas from these basins is generally sourced directly into Front Range markets, traded at the Cheyenne Hub, or requires other export markets. Recently, expansions on the Williston Basin Pipeline and new Bison Pipeline have targeted delivery into Northern Border Pipeline to reach Midwest markets and pricing.
Gathering Systems/Plants | Owner/Operator | Capacity | Commercial Role |
Lost Creek Gathering Lost Cabin Gas Plant | Crestone (ONEOK)/ConocoPhillips Elkhorn Field Services | 0.275 Bcf/d 0.333 Bcf/de | Wind River receipts Process/Treat Wind River receipts for H2S, CO2 Delivery: WIC, CIG |
Big Horn Gas Gathering Big Horn/Byron Gas Plant | Copano/Crestone (ONEOK) | 0.250 Bcf/d 0.3 Bcf/d | Big Horn receipts to Ft. Union gathering system Big Horn gas treatment |
Beaver Creek Plant | Devon Energy | 0.06 Bcf/d | Process/Treat Wind River receipts for H2S, CO2 |
Ft. Union Gas Gathering | Copano/Anadarko/Bargrath/Crestone (ONEOK) | 1.28 Bcf/d | Big Horn/Powder River receipts to market pipelines |
Ft. Union Plant | Anadarko/WGR | 0.75 Bcf/d | Treat gas (CO2)/Delivery: KMIGT, CIG, WIC |
Bear Paw Energy | ONEOK | 0.1 Bcf/d | Powder River receipts |
Thunder Creek Gas Services | Devon/Kinder Morgan | 0.45 Bcf/d | Powder River receipts |
Powder River CBM Gathering | Anadarko/WGR | 0.05 Bcf/d | Powder River receipts to Ft. Union, MIGC, Thunder Creek |
Rimrock Pipeline | Rimrock Energy | 0.1 Bcf/d | Powder River receipts into Thunder Creek |
Bitter Creek Pipeline (PRB) | MDU subsidiary | 0.2 Bcf/d | Powder River receipts to Thunder Creek, Williston Basin Pipeline |
Colorado Interstate (Wind River Lateral) | El Paso | 0.09 Bcf/d | Wind River receipts to CIG mainline |
Colorado Interstate (Powder River Lateral) | El Paso | 0.055 Bcf/d | Powder River receipts to CIG mainline |
Wyoming Interstate (Powder River Lateral) | El Paso | 0.05 Bcf/d | Powder River receipts to WIC mainline |
Wyoming Interstate (Medicine Bow Lateral) | El Paso | 1.5 Bcf/d | Powder River receipts to WIC mainline/Cheyenne |
Douglas Gas Gathering KM Douglas Plant | DCP Midstream Kinder Morgan Interstate | 0.06 Bcf/d 0.145 Bcf/d | Gather rich gas from Powder River area Processing and treating; Delivery: KMIGT |
Shute Creek Processing Plant | ExxonMobil | 0.7 Bcf/d | Process/Treat gas from LaBarge field for H2S removal, CO2 removal and reinjection, helium extraction, etc. Receipt/Delivery: NWP |
HiLight Gas Gathering HiLight/Newcastle Gas Plants | Western Gas Resources | 0.04 Bcf/d 0.03 Bcf/d | Gather Powder River gas Process Powder River volumes, fractionator Delivery: MIGC |
Regional Exit Pipelines | Owner/Operator | Capacity | Commercial Role |
Colorado Interstate Mainline | El Paso | 0.6 Bcf/d | Upstream receipts to utility systems, pipelines in Cheyenne Hub area |
Wyoming Interstate Mainline (including Medicine Bow lateral) | El Paso | 2.2 Bcf/d | Upstream receipts to utility systems, pipelines in Cheyenne Hub area |
KM Interstate | Kinder Morgan | 0.2 Bcf/d | Wind River receipts to KMIGT downstream markets |
KM Pony Express | Kinder Morgan | 0.25 Bcf/d | Powder River receipts to KMIGT downstream markets |
MIGC | Anadarko | 0.175 Bcf/d | Powder River receipts to WBI, CIG, WIC, KMIGT |
Grasslands Pipeline/Expansion | MDU Resources | 0.213 Bcf/d | Powder River receipts to WBI, Northern Border Pipeline (NBPL) |
Bison Pipeline (Jan. 2011) | TransCanada | 0.477 Bcf/d | Powder River receipts to NBPL |
Northeast Colorado/Denver-Julesburg Basin
Located more proximate to the Front Range and regional delivery markets, gas from northeast Colorado and the Denver-Julesburg Basin (1.3 to 2.4 trillion cubic feet of resource potential) can access local markets or choose to compete for export capacity. In general, these volumes access Front Range markets, trade at the Cheyenne Hub or seek export to other markets.
Gathering Systems/Plants | Owner/Operator | Capacity | Commercial Role |
Gilcrest Gathering Gilcrest Plant | AKA Energy | 0.02 Bcf/d 0.02 Bcf/de | DJ Basin receipts Process DJ Basin receipts, fractionator Delivery: CIG, PSCO |
Bitter Creek Pipelines (CO) | MDU Resources | 0.15 Bcf/d (est.) | Process gas from Bonny/Niobrara fields Delivery: Southern Star, KMIGT, Cheyenne Plains |
BP Wattenberg System BP Wattenberg Plant | BP | 0.2 Bcf/d 0.2 Bcf/d | DJ Basin receipts Process DJ receipts; Delivery: PSCO |
Multiple processing plants: Greeley Plant; Roggen; Eaton; Mewbourne; Lucerne; Platteville; Spindle | DCP Midstream | 0.5 Bcf/d 0.03 Bcf/d 0.067 Bcf/d 0.01 Bcf/d 0.4 Bcf/d 0.065 Bcf/d 0.04 Bcf/d | Process and deliver DJ receipts Delivery: PSCO |
Wattenberg System | Western Gas Partners/Anadarko | 0.275 Bcf/d | Gather both wet and dry DJ Basin receipts |
Ft. Lupton Plant | Encana | 0.09 Bcf/d | Process and deliver DJ Basin receipts Delivery: PSCO |
Regional Exit Pipelines | Owner/Operator | Capacity | Commercial Role |
Southern Star Central | Southern Star | 0.195 Bcf/d | Delivery to downstream markets in Kansas |
KMIGT | Kinder Morgan | 0.15 Bcf/d | Delivery to downstream markets in Kansas |
Cheyenne Plains | El Paso | 0.74 Bcf/d | Delivery to downstream markets in Kansas, Okla. |
Local Utility: PS Colorado Front Range Pipeline | Excel Energy | Not Available 0.42 Bcf/d | Delivery to Denver-area markets |
Local Utility: SourceGas | SourceGas Distribution, LLC | Not Available | Delivery to markets |
Raton Basin/Southeastern Colorado
Located in far southeastern Colorado and northern New Mexico, the Raton Basin (0.9 to 1.9 trillion cubic feet of resource potential) is connected only to the Colorado Interstate Gas pipeline system. As such, these volumes have avoided some of the export-capacity constraints and historical pricing issues of other Rockies regions, but they have encountered their own regional constraints on the CIG system.
Volumes produced in the region have generally flowed via CIG into markets in Kansas, Oklahoma, and Texas. However, CIG has recently provided a limited “backhaul” capability by implementing a 16-inch pipe northward from the Raton area to connect to its system that is more proximate to the Front Range and Cheyenne Hub; the capacity is 0.135 Bcf/d. There, Raton volumes can access a broader array of markets and compete for market share. Pioneer Resources, the largest developer/operator in the Raton Basin, has currently suspended future Raton development to focus on other areas. Overall lower gas prices expected in the U.S. over the next few years are likely to keep new development in this area idled. The current infrastructure is adequate to support current production levels.
Gathering Systems/Plants | Owner/Operator | Capacity | Commercial Role |
CIG - Nitrogen Blending Unit CIG Picketwire lateral/various | Colorado Interstate | 0.03 Bcf/d 0.13 Bcf/d | Blend N2 to get gas to pipeline quality Additional gathering capability; Raton gas |
Pioneer Gas Gathering | Pioneer | 0.25 Bcf/d | Gather and treat Raton gas; provide for water handling capability |
Regional Exit Pipelines | Owner/Operator | Capacity | Commercial Role |
Colorado Interstate Mainline | El Paso | 0.25 Bcf/d | Delivery to downstream markets in KS, Okla., TX via CIG |
Colorado Interstate (New Lateral) | El Paso | 0.135 Bcf/d | Delivery to Front Range/Cheyenne Hub to access broader markets |
Piceance Basin, Colorado
The Piceance Basin (12- to 21 trillion cubic feet of resource potential) in Colorado, often combined (geologically speaking) with the Uinta Basin, is one of the three-largest resource areas in the Rockies. The Uinta-Piceance Basin geology provides for development of coalbed methane as well as tight-sand resources.
To date, much of the development in the Piceance is focused on tight sands. The terrain is difficult, and the geology is quite complex. Producing operators in the region have been very successful, but area development has slowed due to current and expected low gas prices. Some of the gas in this area routes to the Meeker/Greasewood area, where it is processed or treated at Enterprise’s Meeker gas plant and can interconnect to the Rockies Express Pipeline to move to markets in the eastern U.S.
At Meeker, the White River trading hub has recently been implemented to provide for additional flexibility, as gas can also be routed toward Questar’s Clay Basin storage or into Kern River Pipeline to access western markets. Activity in this area has been bolstered by gas liquids.
Gathering Systems/Plants | Owner/Operator | Capacity | Commercial Role |
Piceance Creek Gathering Meeker Treating & Processing Plant | Enterprise Products | 1.6 Bcf/d 1.5 Bcf/de | Gather Piceance gas to Meeker processing/treating plant Process/treat Piceance volumes; NGL disposition Delivery into REX Pipeline |
Great Divide Gathering | Enterprise Products | 0.7 Bcf/d | Gathers southern area and Mamm Creek gas Delivery: Piceance Creek gathering |
Collbran Gas Gathering Anderson Gulch Plant | DCP Midstream/others DCP Midstream Partners/others | 0.2 Bcf/d 0.12 Bcf/d | Gathers Collbran Valley gas Treat/compress (only) Collbran Valley gas Delivery: Piceance Creek gathering |
Rangely Foundation Creek Plant | Energy Transfer | 0.05 Bcf/d | Process/treat Piceance Gas; Delivery: NWP |
Northwest Pipeline (Parachute Lateral) Parachute Area Gathering Willow Creek Plant Parachute Creek Plant (3) Treating Facilties | Williams Partners | 0.3 Bcf/d 0.75 Bcf/d 0.45 Bcf/d 0.45 Bcf/d 1.2 Bcf/d | Gather Piceance volumes Gather Piceance volumes to Parachute/Willow Creek plants Process Piceance volumes Process/treat Piceance volumes |
Grand Valley Gathering | Williams Partners (from Barrett) | 0.5 Bcf/d | Gather Piceance volumes |
Encana East Mamm Creek Area Gathering Encana East Mamm Creek Plant | Encana | 0.8 Bcf/d 0.275 Bcf/d | Gather Piceance volumes; water handling Treat/compress Piceance volumes |
Dragon Tail Gathering Dragon Tail Plant | Encana | 0.5 Bcf/d 0.06 Bcf/d | Gather Piceance volumes Process Piceance volumes |
Various gathering systems (6) area processing plants | Energy Transfer (from Canyon Gas) | 0.3 Bcf/d 0.09 Bcf/d | Gather Piceance volumes Process Piceance volumes |
N. Douglas Creek Gas Plant | Wildhorse Energy Partners | 0.02 Bcf/d | Process/treat Piceance volumes |
Regional Exit Pipelines | Owner/Operator | Capacity | Commercial Role |
Rockies Express | Kinder Morgan JV | 1.0 Bcf/d | Piceance gas to REX downstream |
Questar Pipeline (East of Greasewood) Questar Pipeline (West of Greasewood) | Questar | 0.25 Bcf/d 0.35 Bcf/d | Piceance gas to White River Hub/Greasewood Deliveries to Questar system and/or Kern River |
Northwest Pipeline | Williams/Williams Partners | 0.5 Bcf/d | Delivery to downstream markets |
TransColorado | Kinder Morgan | 0.6 Bcf/d | Connection to Greasewood Hub |
White River Hub | Enterprise | 3.0 Bcf/d | Hub/trading center for Piceance gas |
Colorado Interstate (Lateral) | El Paso | 0.195 Bcf/d | Piceance gas to downstream markets |
Wyoming Interstate (Lateral) | El Paso | 0.55 Bcf/d | Piceance gas to downstream markets |
Uinta Basin, Utah
Historically, volumes developed in this area have been severely impacted by local infrastructure and area pipeline-capacity constraints. However, recent projects and expansions now provide capability and flexibility to access multiple markets.
For example, producers can move gas north from the area and can access pipelines to route west to Opal or east to Cheyenne. Also, gas can flow westward on the Questar Pipeline system to access markets at Clay Basin storage or can be routed via Questar’s Southern System into Kern River Pipeline.
Finally, with access to the White River Hub at Greasewood, gas can seek markets there or access pipeline capacity to markets elsewhere. This flow flexibility may be enhanced further as Questar Pipeline considers additional expansion of its Southern System to provide additional capacity into Kern River or Opal.
Gathering Systems/Plants | Owner/Operator | Capacity | Commercial Role |
various gathering systems Chipeta Plant | Anadarko/Ute Energy | 0.6 Bcf/d 0.49 Bcf/de | Gather Uinta gas volumes Process Greater Natural Buttes field volumes Delivery: CIG, WIC, QPC |
Uinta Basin Field Services | Southern Utes/QEP Field Services FIML Resources | 0.1 Bcf/d | Gather Uinta gas volumes |
QEP Gas Gathering Stagecoach Plant Stagecoach/Iron Horse Plant (Q1, 2011) | QEP Field Services | 0.5 Bcf/d 0.22 Bcf/d 0.15 Bcf/d | Gather Uinta volumes Process/blend Uinta volumes; Delivery: QPC Process Uinta volumes; Delivery: QPC |
Wilkin Ridge/West Desert Gathering Riverbend Plant | Monarch Natural Gas | 0.06 Bcf/d 0.05 Bcf/d | Gather Uinta volumes Process Uinta volumes; Delivery: QPC |
Regional Exit Pipelines | Owner/Operator | Capacity | Commercial Role |
Questar Pipeline | Questar | 0.5 Bcf/d | Uinta volumes to market |
Wyoming Interstate (Lateral) | El Paso | 0.56 Bcf/d | Uinta volumes to WIC/OT |
Colorado Interstate (Lateral) | El Paso | 0.15 Bcf/d | Uinta volumes to Greasewood Hub |
Northwest Pipeline | Williams/Williams Partners | 0.3 Bcf/d | Uinta volumes to market |
San Juan Basin, New Mexico
The San Juan Basin in New Mexico (41- to 50.4 trillion cubic feet) has seen development of coalbed-methane gas resources spurred significantly by federal tax credits for many years. Yet, as those credits have expired, development has slowed. Since 1988, the development of the Fruitland coal seam has proved to be the major supply dynamic.
Gathering Systems/Plants | Owner/Operator | Capacity | Commercial Role |
Red Cedar Gas Gathering | Southern Ute/KM Partners | 0.75 Bcf/d | Gather, compress, treat (CO2) San Juan gas |
Enterprise (various gathering acquired from El Paso) Chaco Gas Plant | Enterprise | 1.5 Bcf/d 0.7 Bcf/d | Gather, compress, treat (CO2) San Juan gas Process San Juan area volumes |
Four Corners Gathering Ignacio Plant Kutz and Lybrook Plants Milagro and Esperanza Plants | Williams Partners | 1.5 Bcf/d 0.45 Bcf/d Total: 0.3 Bcf/d Total: 0.75 Bcf/d | Gather San Juan area gas Process San Juan area volumes Process San Juan area volumes Treat (CO2) San Juan area volumes |
Florida River Plant | BP | 0.5 Bcf/d | Gather, compress, treat (CO2) San Juan gas |
Val Verde Gathering | Enterprise (from Burlington via TEPPCO) | 1.0 Bcf/d | Gather, compress, treat (CO2) San Juan gas |
Regional Exit Pipelines | Owner/Operator | Capacity | Commercial Role |
TransColorado | Kinder Morgan | 0.2 Bcf/d | San Juan receipts into TC |
El Paso Pipeline | El Paso | 2.8 Bcf/d | San Juan receipts to western markets |
Transwestern | Energy Transfer | 1.6 Bcf/d | San Juan receipts to western markets |
Northwest Pipeline | Williams/Williams Partners | 0.2 Bcf/d | San Juan receipts into NWP |
Southern Trails Pipeline | Questar | 0.14 Bcf/d | San Juan receipts to California border |
Paradox Basin, Utah
The Paradox Basin in Utah (0.93- to 2.02 trillion cubic feet) appears to have the smallest resource potential in the Rockies. Development here will depend on a higher-than-average gas price to support area development. Questar Pipeline provides the take-away capacity, but would have to be expanded if development exceeds forecast potential. (See Table 10.)
As evidenced by the overall Rockies gas-resource potential, its significant midstream assets and key market players, this region will continue to be a critical factor in the U.S. gas-supply base. Resources have developed over time to support individual needs while becoming more integrated, helping to lessen regional capacity constraints.
Gas trading and transportation capacity have been addressed and are supported. Though supply development in some areas may require additional midstream resources, macro infrastructure in the region should be sufficient to support development needs.
Gathering Systems/Plants | Owner/Operator | Capacity | Commercial Role |
Lisbon Gathering Lisbon Valley Plant Encana Pipeline | Encana | 0.1 Bcf/d 0.06 Bcf/d 0.15 Bcf/d | Lisbon field receipts |
North Project Area Gathering South Project Area Gathering Abajo Gas Transmission | Lynden Energy | 0.1 Bcf/d | Paradox receipts |
Greentown Project Pipeline Greentown Project Plant | Delta Petroleum | 0.1 Bcf/d 0.03 Bcf/d | Paradox receipts Process gas; NGL disposition |
Regional Exit Pipelines | Owner/Operator | Capacity | Commercial Role |
Questar Pipeline | Questar | 0.5 Bcf/d | Paradox receipts to market |
Greentown Pipeline (Market) | Delta Petroleum | 0.05 Bcf/d | Greentown Project volumes to market |
This article has been brought to you by Hart Energy's Midstream Business
Recommended Reading
Rystad: 12 MMbbl/d at Risk in Full-blown Middle East War
2024-10-17 - A full-blown war in the Middle East could end up with 12 MMbbl/d of oil at risk—leading to high prices and widespread global consequences, according to Rystad Energy.
EQT’s Rice: ‘Wake Up’ to Anti-Energy Movement
2024-11-08 - In the face of growing opposition to fossil fuels and energy infrastructure, EQT CEO Toby Rice pulled out a rallying cry at Hart Energy’s DUG Appalachia conference: “Wake up!”
Hirs: Expansive Energy Policies Set to Shape 2025 Markets
2024-12-27 - The incoming administration’s policies on sanctions, tariffs, regulations and deportations will impact the oil and gas industry.
Moelis’ Cantor: Trump to Make American Energy Investable Again
2024-11-06 - Former GOP Majority Leader Eric Cantor, vice chairman and managing partner at Moelis, said EV subsidies are likely to be in the president’s crosshairs in his second term.
Trump vs. Harris—Policy Promises vs. Economics
2024-10-22 - The presidential debate did not shed much light on policy initiatives. Are there substantive differences?
Comments
Add new comment
This conversation is moderated according to Hart Energy community rules. Please read the rules before joining the discussion. If you’re experiencing any technical problems, please contact our customer care team.