Australia’s Santos Ltd., the operator of the Pikka Unit joint venture in Alaska, expects initial production from Pikka Phase 1 to start by 2026, according to the Adelaide-based company’s Managing Director and CEO Kevin Gallagher.
Pikka Phase 1, located on the North Slope of Alaska, includes a single drill site, an oil processing facility and other infrastructure to support production of 80,000 bbl/d, according to Santos.
“The Pikka project has made excellent progress over the winter months in Alaska,” Gallagher said in the company’s first quarter 2024 financial statement.
Gallagher said Pikka was a world-class project — like the Barossa gas project offshore Singapore— and would be transformative for Santos and provide the company with long-term, stable cash flows over the next 10 years to 15 years.
Santos announced its $2.6 billion final investment decision (FID) for Pikka in August 2022. Santos’ share of the FID is $1.3 billion, according to the company’s website. Santos is 51% owner of Pikka Phase 1 in partnership with Spain’s Repsol which holds the remaining 49% of the project.
Pikka Phase 1 progress
According to Santos, the Nanushuk play in the Pikka Unit represents one of the largest conventional oil finds in the U.S. in the past 30 years. Pikka Phase 1 is the most significant development on Alaska’s North Slope in more than 20 years, Santos said on its website.
For Santos, Pikka Phase 1 adds diversity to the company’s portfolio and reduces geographic concentration risk, according to the company. For Repsol, Pikka Phase 1 offers the Spanish company an advantaged onshore position and low carbon intensity production (12 kgCO2/boe), the European energy giant said during its fourth-quarter 2023 webcast.
At the end of first-quarter 2024, work related to Pikka Phase 1 was 47% complete, Santos said in the financial statement.
During the quarter, Santos completed rig operations on seven wells, of which four have been stimulated with three successfully flowing back at favorable rates compared to pre-drill expectations.
Vertical support members for the pipeline are more than 65% complete and pipelaying was more than 61% complete for the winter season objectives. The seawater treatment plant was 62% complete at the end of the quarter, Santos said.
The development plan for Pikka Phase 1 will generate a small surface footprint, according to Santos, and utilize existing infrastructure, including the Kuparuk transportation pipeline and the Trans-Alaska pipeline system.
Recommended Reading
Valveworks Adds Choke Product Offerings with Lancaster Acquisition
2024-11-25 - Valveworks USA is acquiring Lancaster Flow Automation to add choke and flow-control automation technology to its product offerings.
TotalEnergies Pauses Business with Adani, Says it was Not Aware of US Investigation
2024-11-25 - French oil major TotalEnergies SE was not informed of a U.S. investigation into possible bribery and corruption at Adani Green Energy Ltd., it said on Nov. 25, adding it will stop financial contributions to its Adani Group investments following last week's indictment.
ONEOK Announces $4.3B Deal to Acquire Remaining EnLink Stock
2024-11-25 - ONEOK’s deal to acquire the remaining stake in EnLink is expected to close in the first quarter of 2025.
LandBridge Closes Deal for 5,800 Acres in New Mexico's Delaware Basin
2024-11-22 - LandBridge said it announced or closed acquisitions totaling 53,080 acres in fourth-quarter 2024.
ConocoPhillips Completes $22.5B Acquisition of Marathon
2024-11-22 - ConocoPhillips CEO Ryan Lance said he expects synergies of more than $1 billion on a run rate basis over the next 12 months.
Comments
Add new comment
This conversation is moderated according to Hart Energy community rules. Please read the rules before joining the discussion. If you’re experiencing any technical problems, please contact our customer care team.