The U.S. Supreme Court declined a request for further review of a suit challenging the authority of the Federal Energy Regulatory Commission’s eminent domain authority, brought by landowners along the route of the Mountain Valley Pipeline in Virginia.
The Justices released their decision on May 20, according to court documents.
The decision was the latest in one of several lawsuits that inhibited progress on the MVP project until Congress included a provision in a debt bill in 2023 directing agencies to grant the required environmental permits for completion.
The Mountain Valley Pipeline is a 303-mile, 2 Bcf/d natural gas line stretching from Northwestern West Virginia to Southern Virginia. The system is a joint venture between Equitrans Midstream, NextEra Energy, and utilities Consolidated Edison, RGC Resources and AltaGas. Equitrans will operate the pipeline. The line is considered crucial for opening up Appalachian Basin natural gas to markets in the Mid-Atlantic and Southeast U.S.
The FERC has authority over the pipeline as it crosses state borders. In 2020, property owners brought suit, arguing that FERC does not have constitutional authority to condemn their land for the pipeline path. FERC chose not to respond to the petition.
The May 20 decision marked the second time the Supreme Court had reviewed the case. In April 2023, the Supreme Court sent the petition back to an appellate court after the lower court dismissed the case. The courts did not rule on the FERC’s authority, deciding instead that the case had been filed too late, according to a Reuters report.
The appeals court rejected the case again in February. On May 20, the Supreme Court decided not to review it again.
The MVP is expected to be completed by the end of the second quarter of 2024.
Recommended Reading
Supreme Court’s Uinta Basin Rail Case Raises Stakes for LNG, Pipelines
2024-07-10 - The lawsuit, involving crude transport via railway in the Uinta Basin, is part of a larger intragovernmental fight that could have implications for how FERC decides pipeline and LNG plant permitting.
FERC Re-affirms Tellurian Extension Request for Driftwood LNG
2024-07-09 - The Federal Energy Regulatory Commission upheld its earlier decision following the Sierra Club’s request for another hearing on Driftwood LNG’s 2029 completion date.
FERC Approves Transco Expansion in Texas, Louisiana
2024-07-01 - Williams Cos. plans to finish the $91.8M Transcontinental Gas Pipeline project in early 2025.
NextDecade CEO: LNG Ruling Risks Viability of All FERC Projects
2024-08-14 - NextDecade Chairman and CEO Matt Schatzman said an Aug. 6 ruling by the U.S. Court of Appeals for the D.C. Circuit to vacate its FERC permit has “far-reaching implications” that could undercut capital investment in LNG projects.
Bipartisan Bill Aims to Speed Up Permitting Bureaucracy
2024-07-23 - If passed, the new rules would tackle litigation delays for energy projects across all sectors, an analyst says.