U.S. regulators have given National Fuel Gas Co. (NFG) more time to build its proposed Northern Access natural gas pipeline project in Pennsylvania and New York.
The U.S. Federal Energy Regulatory Commission (FERC) on June 29 approved NFG’s January request for a 35-month extension to build the project by December 2024.
Northern Access is one of several fossil fuel projects held up by regulators in New York over the past several years. Others include Williams Cos. Inc.’s Northeast Supply Enhancement and Constitution gas pipelines.
“Due to the passage of time, including extensive litigation delays, we are in the process of evaluating our next steps,” NFG spokesperson Karen Merkel said, noting she could not comment on the current expected cost of the project.
When first proposed, NFG expected the project to cost about $500 million.
FERC approved the project in February 2017 and said NFG had to put it in service by February 2019.
NFG, however, did not build the project because it could not get a water quality certificate from the New York State Department of Environmental Conservation (NYSDEC).
In November 2018, NFG asked FERC for more time to complete construction due to the delay in getting the water quality certificate. In January 2019, FERC gave NFG until February 2022 to finish the project.
In October 2020, NFG asked FERC for another extension until December 2024 to complete the project, but FERC dismissed that request as premature.
NFG made the current request for more time to finish the project in January 2022 after a court determined the NYSDEC waived its water quality certification authority by waiting too long to act on the company's request.
Northern Access, which includes a 99-mile (159-km) pipeline, is designed to deliver about 0.49 Bcf/d of gas from the Marcellus shale in Pennsylvania to New York.
Recommended Reading
Phillips 66 Buys EPIC’s Permian NGL Midstream Assets for $2.2B
2025-01-07 - Phillips 66 will buy EPIC’s NGL assets, including a 175,000 bbl/d pipeline that links production supplies in the Delaware and Midland basins and the Eagle Ford Shale to Gulf Coast fractionation complexes.
Martin Midstream Terminates Merger Agreement Following Pushback
2024-12-29 - Martin Midstream Partners will continue operating as a standalone publicly traded company following termination of its deal to merge with Martin Resource Management Corp.
Allete Gets OK From FERC for $6.2B Sale to Canada Pension Plan, GIP
2024-12-20 - Allete Inc. announced its acquisition by the Canada Pension Plan Investment Board and Global Infrastructure Partners in May.
Exxon Mobil Completes Purchase of FPSO Offshore Guyana
2024-12-19 - Exxon Mobil Corp. paid $535 million to SBM Offshore for the FPSO, which will operate the unit through 2033.
ConocoPhillips to Sell Interests in GoM Assets to Shell for $735MM
2025-02-21 - ConocoPhillips is selling to Shell its interests in the offshore Ursa and Europa fields in the Gulf of Mexico for $735 million.
Comments
Add new comment
This conversation is moderated according to Hart Energy community rules. Please read the rules before joining the discussion. If you’re experiencing any technical problems, please contact our customer care team.