EQM Midstream Partners LP said on May 14 it still sees a “narrow path” to complete its long-delayed $5.4 billion Mountain Valley natural gas pipeline from West Virginia to Virginia by late 2020.
Analysts, however, said Mountain Valley and other pipelines would probably be delayed by a decision by a federal judge in Montana that the U.S. Army Corps of Engineers did not comply with the Endangered Species Act.
EQM said in its first quarter earnings that Mountain Valley “is working through the project’s remaining legal and regulatory challenges to achieve the targeted late 2020 full in-service date.”
When EQM started construction in February 2018, it estimated Mountain Valley would cost about $3.5 billion and be completed by the end of 2018.
But successful legal challenges by environmental and other groups to federal permits resulted in lengthy delays and higher costs for Mountain Valley and other gas pipes under construction like Dominion Energy Inc.’s $8 billion Atlantic Coast from West Virginia to North Carolina.
Then, on April 15, Chief U.S. District Judge Brian Morris ruled that the Army Corps violated federal law by issuing Nationwide Permits to cross bodies of water without adequately consulting other agencies on risks to endangered species and habitat.
Although that ruling was in a case involving TC Energy Corp.’s long-delayed Keystone XL crude pipeline from Canada to the U.S. Midwest, the judge applied the decision to the Army Corps’s handling of the Nationwide Permit program.
This week, the judge refused to limit his decision to just the Keystone case. The U.S. Justice Department then asked the U.S. Court of Appeals for the Ninth Circuit to stay the lower court’s ruling.
Analysts at Height Capital Markets in Washington said they were “skeptical” the Ninth Circuit will stay the Montana judge’s order and noted the court may not decide the case until 2021.
That would push the in-service date for Mountain Valley to at least mid-2021 and could also prevent Dominion’s Atlantic Coast from entering service in early 2022 as planned, Height Capital Markets said.
Analysts at Jefferies said “there is a silver lining for Mountain Valley as a delay in the Nationwide Permit process reduces Atlantic Coast’s likelihood due to potentially significant cost increases ... A 2023 expansion of Mountain Valley is more likely if Atlantic Coast is abandoned.”
Officials at Dominion said the company still expects “to resume construction this summer and be in-service in early 2022.”
Recommended Reading
Trinasolar Develops Tandem Solar Module That Exceeds 800W
2025-03-28 - The 3.1-sq-m module was made with perovskite/silicon tandem solar cells, Trinasolar says.
Woodside Divests Greater Angostura Assets to Perenco for $206MM
2025-03-28 - The Greater Angostura field produces approximately 12% of Trinidad and Tobago’s gas supply, said Woodside CEO Meg O’Neill in a press release.
Phillips 66 Director Criticizes Activist Investor Elliott Amid Proxy Battle
2025-03-28 - A boardroom battle between U.S. refiner Phillips 66 and activist investor Elliott Investment Management has intensified with a Phillips 66 independent director leveling criticisms at Elliott in an open letter to shareholders.
Glenfarne Deal Makes Company Lead Developer of Alaska LNG Project
2025-03-28 - Glenfarne Group LLC is taking over as the lead developer of the Alaska LNG project with the acquisition of a majority interest in the project from Alaska Gasline Development Corp.
Mentor Buys Diamondback-Operated Royalty Acres in Permian
2025-03-28 - Mentor Capital Inc. has purchased a 25.127 net royalty acre stake in West Texas’ Permian Basin.