EQM Midstream Partners LP delayed the expected completion of its Mountain Valley natural gas pipeline from West Virginia to Virginia to early 2021 and said it could boost the $5.4 billion project’s cost by 5% to around $5.7 billion.
Industry analysts, however, said Mountain Valley and other U.S. pipelines will likely be delayed even further by a Montana court’s decision that the U.S. Army Corps of Engineers did not comply with the Endangered Species Act.
EQM, which changed the projected in-service date in a statement issued late June 11, had previously said it expected Mountain Valley to enter service in late 2020.
“We are confident in the ultimate completion of this important infrastructure project,” EQM COO Diana Charletta said, noting it was about 92% complete.
When EQM started construction in February 2018, it estimated Mountain Valley would cost about $3.5 billion and be completed by the end of 2018.
But successful legal challenges to federal permits resulted in lengthy delays and higher costs for Mountain Valley and other gas pipes, like Dominion Energy Inc.’s $8 billion Atlantic Coast line from West Virginia to North Carolina.
Analysts at Height Capital Markets in Washington said on June 12 that EQM’s new in-service date and potential cost increase are optimistic given legal issues with the Army Corps’ Nationwide Permit 12 program, which Mountain Valley intends to use to cross the remaining 10 miles of water bodies along its route.
In April, a Montana judge ruled the Army Corps violated federal law by issuing Nationwide Permits to cross water bodies without adequately consulting other agencies on risks to endangered species and habitat.
“Besides the (Nationwide Permit) issue, Mountain Valley faces litigation risk on several upcoming permitting decisions,” Height Capital Markets said, noting the project will likely enter service in second-quarter 2021.
Recommended Reading
US Drillers Cut Oil, Gas Rigs for Third Week in a Row
2024-10-04 - The oil and gas rig count fell by two to 585 in the week to Oct. 4.
EY: How AI Can Transform Subsurface Operations
2024-10-10 - The inherent complexity of subsurface data and the need to make swift decisions demands a tailored approach.
Bowman Consulting to Manage, Monitor Delaware Basin Wells
2024-10-14 - Bowman Consulting Group’s scope of work includes conducting detailed field surveys of above-ground infrastructure assets across well sites of up to to 8 acres.
E&P Highlights: Oct. 7, 2024
2024-10-07 - Here’s a roundup of the latest E&P headlines, including a major announcement from BP and large contracts in the Middle East.
Classic Rock, New Wells: Permian Conventional Zones Gain Momentum
2024-12-02 - Spurned or simply ignored by the big publics, the Permian Basin’s conventional zones—the Central Basin Platform, Northwest Shelf and Eastern Shelf—remain playgrounds for independent producers.