The U.S. government has adopted rules to protect landowners affected by natural gas pipeline or LNG plant development by forbidding construction until the Federal Energy Regulatory Commission (FERC) acts on requests for rehearing of any decisions for a permit.
The rule, issued late June 9, states that even if a project has all other certifications and permissions to begin construction, it must wait until FERC acts on rehearing requests. The commission has said it would strive to answer rehearing requests within 30 days.
Analysts at Height Capital Markets in Washington said on June 10 that they expect the new rule “will prevent new projects from starting construction for several months while FERC addresses the issues in rehearing requests.”
In the past, while landowners and other stakeholders awaited FERC decisions on rehearing requests, the commission allowed energy companies to use federal eminent domain proceedings to access land and start and sometimes even complete construction.
FERC said some past rehearing requests involved complex issues that required more than 30 days to resolve. In such instances, FERC issued tolling orders granting itself more time to consider the requests.
Analysts at ClearView Energy Partners LLC said FERC probably issued the rule now because it likely expects an adverse ruling in the Allegheny Defense Project vs. FERC case by the U.S. Court of Appeals for the D.C. Circuit, and that “this is a move to secure an outcome more to its liking.”
That case involved an appeal from landowners and other stakeholders against construction of Williams Cos. Inc.’s Atlantic Sunrise gas pipeline project from Pennsylvania to South Carolina.
In that case, FERC allowed Williams to use eminent domain and build the pipe before deciding on rehearing requests. Atlantic Sunrise entered service in 2018.
Recommended Reading
Nabors’ High-spec Rigs Help Keep Lower 48 Revenue Stable in 2Q
2024-07-25 - Nabors’ second quarter EBITDA was down 1% quarter-over-quarter but the company sees signs of increased drilling activity in international markets the second half of the year.
US Rig Count Makes Biggest Monthly Jump Since November 2022
2024-07-26 - The oil and gas rig count, an early indicator of future output, rose by three to 589 in the week to July 26.
US Drillers Cut Oil, Gas Rigs for Fourth Week in a Row
2024-06-28 - The oil and gas rig count fell by seven to 581 in the week to June 28.
US Drillers Cut Oil, Gas Rigs for Third Week in a Row, Baker Hughes Says
2024-08-30 - The rig count is 8% below this time last year, according to Baker Hughes.
US Drillers Cut Oil, Gas Rigs for First Time in Three weeks
2024-08-02 - The oil and gas rig count, an early indicator of future output, fell by three to 586 in the week to Aug. 2. Baker Hughes said that puts the total rig count down 73, or 11%, below this time last year.