WASHINGTON—A federal judge in Montana on Aug. 15 ordered the U.S. State Department to do a full environmental review of a revised route for the Keystone XL crude oil pipeline, a move that could delay the project and prove a setback for the Trump administration.
For more than a decade, environmentalists, tribal groups, and ranchers have fought the $8-billion, 1,180-mile pipeline to carry heavy crude to Steele City in Nebraska from Canada’s oil sands in Alberta.
U.S. District Court Judge Brian Morris ruled for the Indigenous Environmental Network and other plaintiffs, ordering the review of a revised pipeline route through Nebraska to supplement one the department did on the original path in 2014.
In his ruling, Morris said the State Department was obligated to “analyze new information relevant to the environmental impacts of its decision” to issue a permit for the pipeline last year.
Supporting the project are Canadian oil producers, who face price discounts over transport bottlenecks, and U.S. oil interests and pipeline builders.
TransCanada Corp. (NYSE: TRP), which wants to build Keystone XL, did not immediately respond to a request for comment on the ruling. It hopes to start preliminary work in Montana in coming months and begin construction in the second quarter of 2019.
The White House did not immediately respond to a request for comment, nor did the State Department.
The ruling was “a rejection of the Trump administration’s attempt to flout the law and force Keystone XL on the American people,” said Jackie Prange, a lawyer for the Natural Resources Defense Council, an environmental group.
In 2015, then President Barack Obama, a Democrat, rejected the pipeline, saying it would add to emissions that cause climate change and would mostly benefit Canadians.
President Donald Trump, a Republican, pushed to approve the pipeline soon after he took office. A State Department official signed a so-called presidential permit in 2017 allowing the line to move forward.
However, Morris declined the plaintiff’s request to vacate that permit, which was based on the 2014 review.
Last year, Nebraska regulators approved an alternative route for the pipeline which will cost TransCanada millions of dollars more than the original path.
In a draft environmental assessment last month, the State Department said Keystone XL would cause no major harm to water supplies or wildlife. That review is less wide-ranging than the full environmental impact statement Morris ordered.
Recommended Reading
Then and Now: 4D Seismic Surveys Cut Costs, Increase Production
2025-03-16 - 4D seismic surveys allow operators to monitor changes in reservoirs over extended periods for more informed well placement decisions. Companies including SLB and MicroSeismic Inc. are already seeing the benefits of the tech.
E&P Seller Beware: The Buyer May be Armed with AI Intel
2025-02-18 - Go AI or leave money on the table, warned panelists in a NAPE program.
AI Moves into Next Phase of E&P Adoption as Tech Shows Full Potential
2025-03-25 - AI adoption is helping with operations design and improving understanding of the subsurface for big companies. Smaller companies are beginning to follow in their footsteps, panelists said at Hart Energy’s DUG Gas Conference.
Woodside Awards SLB Drilling Contract for Project Offshore Mexico
2025-03-31 - SLB will deliver 18 ultra-deepwater wells for Woodside Energy’s Trion ultra-deepwater project starting in early 2026.
Energy Technology Startups Save Methane to Save Money
2025-03-28 - Startups are finding ways to curb methane emissions while increasing efficiency—and profits.