After a series of setbacks, the companies building the U.S. Mountain Valley natural gas pipeline now plan to seek individual permits to cross each stream remaining in its path, and analysts say that will delay its startup until 2022.
The Mountain Valley line, a $5.8 billion-$6 billion project that stretches from West Virginia to Virginia, is one of a series of energy infrastructure projects that have been delayed by legal opposition and regulatory problems.
Equitrans Midstream Corp., the lead company building the pipeline, said in a federal filing on Jan. 26 that Mountain Valley would seek individual stream crossing permits from the U.S. Army Corps of Engineers, among other things. Those permits became necessary after environmental groups successfully challenged a program that allowed the crossing of a series of streams and rivers under one authorization.
EQT says the line should still be completed by the end of 2021.
"With [Mountain Valley's] total project work roughly 92% complete, we believe that this prudent change in course is the most efficient regulatory path to completing the remaining components of this important natural gas infrastructure project and keeping within our current budget and schedule," Equitrans spokeswoman Natalie Cox said.
Previously, the project relied on the Army Corps' Nationwide Permit 12 program, which covered all stream crossings in one authorization.
Height Capital Markets analysts projected that the additional time needed to file for new permits would push Mountain Valley's in-service date into the first half of 2022.
"We expect the Biden Administration will agree with environmentalists and the Fourth Circuit [Court of Appeals] panel that [Mountain Valley's] Nationwide Permit 12 authorization is flawed and require individual stream crossing permits," analysts at Height Capital Markets said.
When construction of Mountain Valley started in February 2018, Equitrans estimated the 303-mile (487.6-km) pipeline would cost about $3.5 billion and be completed by the end of 2018.
A unit of NextEra Energy Inc., one of the companies involved in the pipeline, took an impairment charge of $1.2 billion on its investment in Mountain Valley due to numerous cost overruns and delays.
Mountain Valley will use pipe 42 inches in diameter to transport 2 Bcf/d of gas from the Marcellus/Utica shale formation in West Virginia, Pennsylvania and Ohio to Virginia. One billion cubic feet is enough to supply about 5 million U.S. homes for a day.
The pipeline project is owned by units of Equitrans, NextEra Energy, Consolidated Edison Inc., AltaGas Ltd. and RGC Resources Inc.
Recommended Reading
Then and Now: 4D Seismic Surveys Cut Costs, Increase Production
2025-03-16 - 4D seismic surveys allow operators to monitor changes in reservoirs over extended periods for more informed well placement decisions. Companies including SLB and MicroSeismic Inc. are already seeing the benefits of the tech.
Pioneer Energy’s Tech Offers More Pad Throughput, Fewer Emissions
2025-01-14 - Pioneer Energy’s Emission Control Treater technology reduces emissions and can boost a well’s crude yield by 5% to10%, executives say.
Aris CEO Brock Foresees Consolidation as Need for Water Management Grows
2025-02-14 - As E&Ps get more efficient and operators drill longer laterals, the sheer amount of produced water continues to grow. Aris Water Solutions CEO Amanda Brock says consolidation is likely to handle the needed infrastructure expansions.
Halliburton, Sekal Partner on World’s First Automated On-Bottom Drilling System
2025-02-26 - Halliburton Co. and Sekal AS delivered the well for Equinor on the Norwegian Continental Shelf.
E&P Highlights: March 3, 2025
2025-03-03 - Here’s a roundup of the latest E&P headlines, from planned Kolibri wells in Oklahoma to a discovery in the Barents Sea.