New York Gov. Andrew Cuomo. (Source: Hans Pennink/Shutterstock.com)
New York environmental regulators on May 15 denied a water permit for Williams Cos. Inc.’s proposed Northeast Supply Enhancement (NESE) natural gas pipeline from Pennsylvania to New York City.
The Department of Environmental Conservation (DEC) said the construction of the project would not meet the state’s rigorous water quality standards.
Williams has said the project, which includes an offshore pipe between New Jersey and Long Island, New York, will cost about $1 billion and could enter service in time for winter 2021 heating season.
Williams said in an email it was disappointed with the decision.
“We continue to believe that the fundamentals of our project align with New York’s clean energy goals because it would have improved local air quality and, at the same time, supported economic development and led to lower heating bills.”
The company did not immediately say what its next steps would be.
In mid-2019, regulators in New York and New Jersey denied Williams’ applications for the permits, called water quality certification, because the project could adversely impact water quality in the New York Bay.
After New York regulators denied the water certification, the U.S. unit of U.K.-energy firm National Grid Plc, which agreed to buy gas from Williams’ pipe, imposed a moratorium in on signing new customers in May 2019.
National Grid, which serves about 1.8 million customers in Brooklyn, Queens, Staten Island and Long Island, said it would not have enough gas to supply existing and new customers without the pipe.
That prompted New York Gov. Andrew Cuomo to threaten to revoke National Grid’s license to operate its gas utility.
Ultimately, National Grid in November agreed to end the moratorium and pay $36 million, most of which it will spend on conservation and clean energy projects.
National Grid also agreed to come up with a plan, part of which was released earlier in May, to meet long-term demand of its downstate gas customers. One of two proposals in that plan included construction of Williams’ NESE pipe by winter 2021-2022.
If built, NESE would add about 37 miles of new pipe and compression to Williams’ existing Transco system and transport an additional 0.4 Bcf/d of gas from Pennsylvania to New York. One billion cubic feet is enough gas for about 5 million U.S. homes for a day.
Recommended Reading
Delivering Dividends Through Digital Technology
2024-12-30 - Increasing automation is creating a step change across the oil and gas life cycle.
E&P Highlights: Jan. 21, 2025
2025-01-21 - Here’s a roundup of the latest E&P headlines, with Flowserve getting a contract from ADNOC and a couple of offshore oil and gas discoveries.
E&P Highlights: Jan. 13, 2025
2025-01-13 - Here’s a roundup of the latest E&P headlines, including Chevron starting production from a platform in the Gulf of Mexico and several new products for pipelines.
E&P Highlights: Feb. 10, 2025
2025-02-10 - Here’s a roundup of the latest E&P headlines, from a Beetaloo well stimulated in Australia to new oil production in China.
E&P Highlights: Dec. 16, 2024
2024-12-16 - Here’s a roundup of the latest E&P headlines, including a pair of contracts awarded offshore Brazil, development progress in the Tishomingo Field in Oklahoma and a partnership that will deploy advanced electric simul-frac fleets across the Permian Basin.