New York environmental regulators on May 15 denied a water permit for Williams Cos. Inc.’s proposed Northeast Supply Enhancement (NESE) natural gas pipeline from Pennsylvania to New York City.
The Department of Environmental Conservation (DEC) said the construction of the project would not meet the state’s rigorous water quality standards.
Williams has said the project, which includes an offshore pipe between New Jersey and Long Island, New York, will cost about $1 billion and could enter service in time for winter 2021 heating season.
Williams said in an email it was disappointed with the decision.
“We continue to believe that the fundamentals of our project align with New York’s clean energy goals because it would have improved local air quality and, at the same time, supported economic development and led to lower heating bills.”
The company did not immediately say what its next steps would be.
In mid-2019, regulators in New York and New Jersey denied Williams’ applications for the permits, called water quality certification, because the project could adversely impact water quality in the New York Bay.
After New York regulators denied the water certification, the U.S. unit of U.K.-energy firm National Grid Plc, which agreed to buy gas from Williams’ pipe, imposed a moratorium in on signing new customers in May 2019.
National Grid, which serves about 1.8 million customers in Brooklyn, Queens, Staten Island and Long Island, said it would not have enough gas to supply existing and new customers without the pipe.
That prompted New York Gov. Andrew Cuomo to threaten to revoke National Grid’s license to operate its gas utility.
Ultimately, National Grid in November agreed to end the moratorium and pay $36 million, most of which it will spend on conservation and clean energy projects.
National Grid also agreed to come up with a plan, part of which was released earlier in May, to meet long-term demand of its downstate gas customers. One of two proposals in that plan included construction of Williams’ NESE pipe by winter 2021-2022.
If built, NESE would add about 37 miles of new pipe and compression to Williams’ existing Transco system and transport an additional 0.4 Bcf/d of gas from Pennsylvania to New York. One billion cubic feet is enough gas for about 5 million U.S. homes for a day.
Recommended Reading
Geopolitical Tensions Complicate Oil Price Predictions
2024-10-14 - Geopolitical tensions around the world are an ongoing wildcard for oil prices in the near-term, according to BOK Financial Securities’ Dennis Kissler. U.S. producers will have to pivot off of whatever hand they are dealt.
Oil and Gas Stocks Revel in a Post-Election Trump Bump
2024-11-08 - Oil and gas company stocks, particularly those of E&Ps and oilfield services, enjoyed a boost immediately following the presidential election of Donald Trump.
FERC OKs Export Capacity Expansion at KMI’s Georgia LNG Plant
2024-11-25 - Kinder Morgan subsidiary Southern LNG’s Elba Island terminal has been granted permission by the Federal Energy Regulatory Commission to go ahead with a 0.4-mtpa production bump.
EPA Gives OK to Texas GulfLink Deepwater Port
2024-11-04 - Sentinel Midstream’s Texas GulfLink project is one of several proposals for an offshore oil terminal in the Gulf.
CNOOC’s Long Lake Northwest Project Begins Crude Production
2024-11-06 - CNOOC’s Long Lake Northwest project will reach a peak production of 8,200 bbl/d of crude in 2025.