MOSCOW—Russia’s Nord Stream 2 gas pipeline project to Germany may launch in 2020, rather than the end of 2019, due to delays in obtaining permits from Denmark, Interfax news agency on May 17 quoted Nord Stream 2 AG as saying.
The Russian-led company has two pending route applications with Danish authorities, the first of which was submitted more than two years ago, but it was asked in March to assess a third route option in Danish waters.
Nord Stream 2 was quoted by Interfax as saying that the launch date could be pushed back to 2020 if it has to pursue the third route scenario.
Nord Stream 2 told Reuters on May 17 it considered it was being illegally forced to apply for a third route. It said it had done so last month, but that it was still hoping for one of the first two routes to be approved.
“The Nord Stream 2 pipeline can certainly be implemented within our timeline,” it said in a statement.
“From the project developer’s perspectives, all prerequisites are met for completion of the project by the end of 2019,” spokeswoman Irina Vasilyeva said in emailed comments.
Nord Stream 2 is led by Russian state gas producer Gazprom, with 50% of the funding provided by Germany’s Uniper and BASF’s Wintershall unit, Anglo-Dutch firm Shell, Austria’s OMV and France’s Engie.
Gazprom declined to comment.
Nord Stream 2 has come under fire from the United States and several eastern European, Nordic and Baltic Sea countries which fear it will increase the European Union’s reliance on Russian gas.
Recommended Reading
EY: How AI Can Transform Subsurface Operations
2024-10-10 - The inherent complexity of subsurface data and the need to make swift decisions demands a tailored approach.
Bowman Consulting to Manage, Monitor Delaware Basin Wells
2024-10-14 - Bowman Consulting Group’s scope of work includes conducting detailed field surveys of above-ground infrastructure assets across well sites of up to to 8 acres.
Classic Rock, New Wells: Permian Conventional Zones Gain Momentum
2024-12-02 - Spurned or simply ignored by the big publics, the Permian Basin’s conventional zones—the Central Basin Platform, Northwest Shelf and Eastern Shelf—remain playgrounds for independent producers.
First Helium Plans Drilling of Two Oil Targets in Alberta
2024-11-29 - First Helium Inc. has identified 10 other sites in the Leduc formation.
DNO Discovers Oil in New Play Offshore Norway
2024-12-02 - DNO ASA estimated gross recoverable resources in the range of 27 MMboe to 57 MMboe.