The COVID-19 pandemic has interrupted the development of Norway’s offshore oil and gas projects, pushing up costs and postponing startups, the government and oil company Equinor said Oct. 7.
The costs of ongoing projects rose by 13.2 billion Norwegian crowns ($1.4 billion) from a year ago on an inflation-adjusted basis, government documents showed, as COVID-19 restrictions stalled construction at several fields.
“The COVID-19 pandemic and weakened Norwegian (currency) have negatively impacted some of the projects, but the combined project portfolio is still very resilient,” Equinor said in a separate statement.
Following the delays, Norway’s oil output for next year is now expected to be 2.15 million barrels per day, slightly less than the 2.24 million predicted for 2021 one year ago, the government’s budget showed.
Gas production is expected to be 117 billion cubic meters (Bcm), less than 121 Bcm forecast a year ago.
Equinor’s Martin Linge oil and gas field is now expected to cost 60.8 billion crowns, up from an estimate of 56.1 billion a year ago, Norway’s 2021 fiscal budget showed.
The company’s Johan Castberg Arctic oil field, meanwhile, is now expected to cost 53.4 billion crowns, up from 49 billion crowns previously, the government said.
Cost overruns also hit Equinor’s Njord Future, Repsol’s Yme and other developments.
In March, the long-delayed Martin Linge development became the first offshore field to be hit by the pandemic when installation work was halted after an employee tested positive for the virus.
Half of the inflation-adjusted cost increase of 3.6 billion crowns for Martin Linge was down to infection control measures, Equinor said.
The pandemic also interrupted construction of the Johan Castberg’s FPSO unit at a yard in Singapore, while the company also discovered technical problems.
Both projects have been delayed by about a year, with Martin Linge now expected to come on stream in the summer of 2021 and Johan Castberg in the fourth quarter of 2023.
The cost of the Njord Future project, which aims to produce an extra 175 million barrels of oil equivalent from Njord, and its tie-back Hyme also rose. The planned startup date has been delayed until next year.
As a result, several smaller projects, which are planning to use the Njord’s production facilities, such as Neptune Energy’s Fenja, will also be delayed.
Recommended Reading
Targa Buys Back Bakken Assets After Strong 2024
2025-02-20 - Targa Resources Corp. is repurchasing its interest in Targa Badlands LLC for $1.8 billion and announced three new projects to expand its NGL system during its fourth-quarter earnings call.
Plains’ $725MM in Deals Add Eagle Ford, Permian Infrastructure
2025-01-08 - Plains All American Pipeline’s executed transactions with EnCap Flatrock Midstream in the Eagle Ford and Medallion Midstream in the Delaware Basin, among other moves.
Kinder Morgan to Build $1.7B Texas Pipeline to Serve LNG Sector
2025-01-22 - Kinder Morgan said the 216-mile project will originate in Katy, Texas, and move gas volumes to the Gulf Coast’s LNG and industrial corridor beginning in 2027.
Kinder Morgan Completes Bakken G&P Acquisition from Outrigger Energy II
2025-02-18 - Kinder Morgan closed on a $640 million deal for a Bakken natural gas gathering and processing network in the Williston Basin.
Kinder Morgan Acquires Bakken NatGas G&P in $640MM Deal
2025-01-13 - The $640 million deal increases Kinder Morgan subsidiary Hiland Partners Holdings’ market access to North Dakota supply.