Erected barriers divide a residential area and the Mariner East 2 pipeline construction site in Chester County, Pa. (Source: Jana Shea/Shutterstock.com)
Pennsylvania environmental regulators ordered Energy Transfer LP’s Sunoco Pipeline unit to reroute a section of the Mariner East 2 NGL pipeline after spilling 8,000 gallons of drilling fluid in Marsh Creek State Park in August.
Analysts at Height Capital Markets said on Sept. 14 the reroute could delay an upgrade to the already operating Mariner East 2 project that was expected to be completed in the second quarter of 2021.
Officials at Energy Transfer were not immediately available for comment.
The Pennsylvania Department of Environmental Protection said late Sept. 11 the Marsh Creek spill caused the park to close 33 acres of the lake from boating and other recreational uses.
“These incidents are yet another instance where Sunoco has blatantly disregarded the citizens and resources of Chester County with careless actions while installing the Mariner East II Pipeline,” DEP Secretary Patrick McDonnell said in a statement.
The reroute order was the latest in a long series of sanctions against the company for violations of its permits during construction of Mariner East 2.
Since May 2017, Pennsylvania has issued 115 notices of violation to Mariner East, mostly for drilling fluid spills, including one in September.
Pennsylvania has fined the company and stopped construction on the pipe several times. Several politicians and local groups have long urged the state to stop work again and shut the pipe.
Mariner East transports liquids from the Marcellus and Utica shales in western Pennsylvania to customers in the state and elsewhere, including international exports from Energy Transfer’s Marcus Hook complex near Philadelphia.
Sunoco started work on the $2.5 billion Mariner East expansion in February 2017 and had planned to finish the 350-mile (563-km) pipeline in the third quarter of 2017.
But completion was delayed until December 2018 due to several work stoppages by state agencies.
Recommended Reading
Tribal Nations Step Away from Enbridge’s Line 5 Process
2025-03-26 - The U.S. Army Corps of Engineers included Line 5 on a list of projects to be considered for emergency permitting. But native groups say the potential emergency designation for the project is unfair.
Ironwood Launches Third Eagle Ford Midstream Co. After January Sale
2025-03-25 - Ironwood Midstream has launched its third iteration after having sold assets to Plains All American in January.
Elliott Sues Phillips 66 to Put Board Nominees Up for Vote
2025-03-25 - Elliott Investment Management has asked a court to order Phillips 66 to require four board seats to stand for election at its annual shareholder meeting.
East Daley: Midstream Investors Drawn to Southeast as Demand Heats Up
2025-03-25 - Competition for gas supply will heat up as demand from data centers and new LNG projects jockey for a spot on takeaway lines.
Venture Global’s Plaquemines Gets FERC Approval for Phase 2 Generators
2025-03-24 - Venture Global continues to ramp up production after an early winter startup.