Almost a decade ago, Equinor recognized that the cost structure for new offshore field developments on the Norwegian Continental Shelf (NCS) was unsustainable. The company set out to reduce costs by at least 25%, and discussions began with service providers about how to achieve this step-change in efficiency.
At the same time, Baker Hughes had been advocating for greater collaboration in the North Sea to achieve better performance at lower cost.
By the time the Johan Sverdrup well construction tender was released in early 2015, Equinor had created a new fully integrated business model aimed at reducing costs and drilling days per well by 50% within three years.
New operating model takes shape
This new model was based on having one main service provider to collaborate closely with the operator and rig contractor to collectively close the gap to the “perfect well.”
Based on this model, Equinor awarded a long-term, integrated drilling and well service contract for Johan Sverdrup to Baker Hughes—the first large-scale contract of its kind on the NCS. Odfjell Drilling was awarded the main rig and rig services contract.
Initially there was trepidation about achieving the project’s ambitious objectives. The three companies created a shared vision to build support and align employees across the partnership—“ONE Team: Perfect Well Deliveries.”
The Johan Sverdrup integrated project was a masterful success that proved the value of integration and collaboration. As a result, in 2017, Equinor expanded its vision and launched tenders to transition all their rigs and assets on the NCS to the integrated model.
With learnings from Johan Sverdrup and new technology and remote operations on the rise, this was the chance to push the integrated approach and transform the offshore industry even further.
IOL3 comes to life
The personnel optimization model called Integrated Operations Level 3 (IOL3) is a new way to leverage the advantages of having one service provider. The concept behind IOL3 is to move any task not physically required to take place at the wellsite onshore.
The goal was to reduce the core crew offshore by 50%, which would radically reduce structural costs, shrink the operational carbon footprint, and improve safety, all while maintaining and even improving service delivery.
To meet the challenge, Baker Hughes reconsidered and fundamentally changed its approach to wellsite roles, and replaced them with new, multi-skilled roles that leveraged more than one technical discipline.
In October 2019, Baker Hughes became the first oilfield service company to transition a rig to IOL3. Baker Hughes shifted half its offshore rig personnel to its ROC in Stavanger. No longer isolated on the rig, these specialists collaborated with other experts in new ways to make better, faster decisions at critical moments in the well construction process. By working remotely, they also avoided the safety risks of working offshore.
Proof of concept
To date, Baker Hughes has transitioned 10 rigs to IOL3 and another three are in transition. About 120 Baker Hughes employees have relocated from rigs to onshore, reducing 900+ helicopter trips, thereby reducing emissions from travel.
At the same time, operational excellence continues. In July 2021, a record-setting well in the Troll field was celebrated by Equinor, Odfjell Drilling, and Baker Hughes. Records include the longest well drilled (10,042 m) and the longest horizontal section (8,033 m).
Baker Hughes is building on its success with Equinor. Earlier this year, bp announced the Clair Alliance, a tripartite agreement with Baker Hughes and Odfjell Drilling to transform well construction activity using IOL3 at the Clair Field, U.K.
Ultimately, Baker Hughes’s goal is to expand the IOL3 model to all its integrated projects worldwide.
The ability to reduce emissions, while improving safety outcomes and operational performance serves as a “proof of concept” that sets the standard for sustainable offshore oil and gas projects in the 2020s and beyond.
Marianne Davenport serves as vice president of Europe and North Sea at Baker Hughes and Chris Jones is the vice president of North America Offshore at Baker Hughes.
Recommended Reading
Halliburton Secures Drilling Contract from Petrobras Offshore Brazil
2025-01-30 - Halliburton Co. said the contract expands its drilling services footprint in the presalt and post-salt areas for both development and exploration wells.
SLB Launches Electric Well Control Tech to Replace Hydraulics
2025-03-04 - SLB says the new systems reduce costs and provide real-time data for operators.
Halliburton, Sekal Partner on World’s First Automated On-Bottom Drilling System
2025-02-26 - Halliburton Co. and Sekal AS delivered the well for Equinor on the Norwegian Continental Shelf.
TGS to Reprocess Seismic Data in India’s Krishna-Godavari Basin
2025-01-28 - TGS will reprocess 3D seismic data, including 10,900 sq km of open acreage available in India’s upcoming 10th Open Acreage Licensing Policy (OALP) bid round blocks.
Artificial Lift Firm Flowco Prices IPO Above Guidance at $427MM
2025-01-15 - Flowco Holdings priced its IPO at $24 per share, above its original guidance. The oilfield services firm will begin trading on the New York Stock Exchange on Jan. 16.
Comments
Add new comment
This conversation is moderated according to Hart Energy community rules. Please read the rules before joining the discussion. If you’re experiencing any technical problems, please contact our customer care team.