Work is already underway on ConocoPhillips’ Willow drilling project on Alaska’s North Slope just days after receiving federal approval.
Houston-based ConocoPhillips has started construction on the gravel roads needed for the multibillion-dollar Willow project in the National Petroleum Reserve-Alaska, a company spokesperson confirmed.
Environmental groups have also been busy, with multiple groups filing lawsuits.
ConocoPhillips hasn’t made an official final investment decision on the project yet, but the E&P company didn’t wait long to get started on construction activities.
President Joe Biden’s administration issued a final record of decision on March 13 approving a scaled-back version of ConocoPhillips’ Willow drilling plan.
ConocoPhillips didn’t get everything it wanted for Willow from the U.S. Department of Interior (DOI) and the Bureau of Land Management. Two of the five proposed drill sites the company proposed for the project were denied.
That substantially reduces the amount of surface infrastructure, including gravel roads, ice roads and pipelines, required to develop and service those two rejected drill sites.
The DOI also signed off on a total of 199 production and injection wells, down from a previous request for 251 total wells.
ConocoPhillips plans to spend between $100 million and $400 million on developing Willow this year, CFO Bill Bullock said in the company’s fourth-quarter earnings call in February.
In addition to starting construction on the gravel roads, the company also planned to ramp up fabrication and supply chain activities immediately after receiving a final decision from the federal government, Andy O’Brien, senior vice president of global operations, said during the call.
O’Brien said ConocoPhillips was still finalizing cost estimates at that time, but anticipated spending between $7 billion and $7.5 billion in order to reach first production at Willow.
That’s up from previous cost estimates due to inflationary pressures and refining the scope of the drilling project from five pads as proposed to accommodate BLM’s preferred three-pad alternative.
Analysts at Piper Sandler said while investors have had mixed opinions on the attractiveness of the scaled-back drilling project, the firm sees the DOI’s approval of Willow “as a clear positive for the company.”
Sajjad Alam, vice president and senior credit officer at Moody’s Investors Service, said the DOI’s approval “will provide the company with another avenue for domestic production growth at relatively low cost.”
The Willow project has faced years of delays. ConocoPhillips acquired the oil and gas leases in the National Petroleum Reserve in Alaska in the late 1990s, but work on Willow began in earnest in 2018 when the U.S. Bureau of Land Management began drafting an Environmental Impact Statement.
The project was eventually approved by the Trump administration in 2020. However, a federal judge later vacated the government’s approval of Willow in 2021, citing issues with the project’s environmental review process.
Administration faces lawsuits
While the administration reduced the scope of Willow, environmental and community advocacy groups claim that the drilling project’s approval undermines President Joe Biden’s climate goals.
More than ten organizations are suing the Biden administration in at least two lawsuits in connection with Willow’s approval.
Six groups – Sovereign Iñupiat for a Living Arctic, Alaska Wilderness League, Northern Alaska Environmental Center, Environment America, Sierra Club and The Wilderness Society – said they had filed a lawsuit in U.S. District Court for the District of Alaska on March 14.
The DOI, BLM and the U.S. Fish & Wildlife Service are listed as defendants, according to court documents.
In a separate lawsuit, other groups – including Greenpeace and the Center for Biological Diversity – allege that the Biden administration failed to properly consider alternatives that would have reduced greenhouse gas emissions on the North Slope, among other concerns.
In addition to several federal agencies, the lawsuit named Interior Secretary Deb Haaland and Secretary of Commerce Gina Raimondo as defendants.
“We believe the BLM and cooperating agencies have conducted a thorough process that satisfies all legal requirements,” ConocoPhillips said in a statement. “The final [Supplemental Environmental Impact Statement] addresses the deficiencies identified in the prior EIS that was the subject of the Federal District Court remand in 2021.”
Recommended Reading
EY: Three Themes That Will Drive Transformational M&A in 2025
2024-12-19 - Prices, consolidation and financial firepower will push deals forward, says EY.
Reliance Exercises Four-Well Option on Transocean Rig
2024-12-18 - Transocean Ltd. says the 270-day program will contribute about $111 million in backlog.
Petrobras Awards Seadrill Two Drillship Contracts Off Brazil
2024-12-18 - Seadrill said the West Jupiter and West Tellus contracts both have a three-year duration and will add nearly $1 billion to the company’s backlog.
QatarEnergy Joins Joint Venture Offshore Namibia
2024-12-17 - QatarEnergy acquired a 27.5% stake in petroleum exploration license 90 offshore Namibia.
DNO Makes Another Norwegian North Sea Discovery
2024-12-17 - DNO ASA estimated gross recoverable resources in the range of 2 million to 13 million barrels of oil equivalent at its discovery on the Ringand prospect in the North Sea.
Comments
Add new comment
This conversation is moderated according to Hart Energy community rules. Please read the rules before joining the discussion. If you’re experiencing any technical problems, please contact our customer care team.