Decommissioning operations have to be carried out in accordance with strict guidelines. Because these projects can be costly, expediting the cleanup process is the operator's goal. The challenge is to perform the work rapidly without compromising safety or the quality of the work.
On a decommissioning project in the North Sea in May 2011, operator ConocoPhillips needed to remove old debris from a 250-m by 250-m (820-ft by 820-ft) area in preparation for the installation of a new platform. The site, which had been in use for 30 years, lies 322 km (200 miles) southwest of Stavanger near the border between the Norwegian and UK sectors of Ekofisk, the oldest field in the North Sea.
PanGeo Subsea was contracted to carry out a post-debris clearance survey with the Sub-Bottom Imager (SBI), an acoustic survey tool that uses an array of five hydrophones with 40 channels, to create a 5-m (16.4-ft) deep by 5-m wide 3-D volumetric image of the sub-seabed.
The tool measures the acoustic return of a buried target and can detect differences in acoustic impedance of varying sedimentary layers. When the impedance of an area is significantly different from its surroundings, the system detects a transition indicating the presence of an object or layer. Although the SBI does not differentiate between compact sands, a boulder, or an object, PanGeo staff apply additional geological, geometrical, and survey information to interpret the SBI data. "Since there are not many geotechnical linear features," explained Alex Fleming, PanGeo vice president Global Operations, "the linear features stand out quite well."
On the North Sea project, the object was to ensure the sub-seabed was cleared of all manmade objects to a depth of 2 m (6.6 ft). This project marked the introduction of the SBI for pipeline decommissioning.

The SBI was launched from a pipelay vessel to carry out imaging of a buried pipeline in the North Sea.
Operations
The debris removal operation included a 200-m (656-ft) section of 30-in. concrete clad pipe and a 200-m section of 4.5-in. bundled pipe (10 in. in total width).
Team members worked 12-hour shifts from a pipelay vessel to carry out the operation. Existing maps were used to locate the 30-in. pipe, but in assessing the area, it was discovered that the coordinates of the 4.5-in. bundled pipe were inaccurate. Assumedly this positional inaccuracy was due to the historical database not being updated as performance and repeatability of surface and subsurface positioning systems continually developed over the years since the pipe was laid.
PanGeo deployed the SBI, mounted on a workclass ROV, at a depth of 80 m (262 ft).
Initial attempts by the PanGeo team to locate the 4.5-in. bundled pipe following the as-given route failed. On reviewing the data, however, the team discovered that the SBI had imaged a section of the pipe that crossed the original survey line. Using a proprietary mosaic, the full survey gridlines had been set 4 m (13 ft) apart, which provided 100% coverage.
"We found the entire length of 4.5-in. bundled pipe in the next pass," said Jody Pynn, PanGeo senior systems engineer. He attributes this to the SBI's ability to image a 3-D volume of a given area. The pipe was found at distances up to 12 m (39 ft) from the as-given coordinates at burial depths as great as 4.5 m (~15 ft), a 3.5-m (~11.5-ft) discrepancy from the map, which indicated a burial depth of 1.5 m (~3.5 ft).
"We were getting immediate feedback from the excavation crew that they found what we said was going to be there," said Gary Dinn, PanGeo vice president of technology development. "That was proof of the success. This was well beyond the ability to image pipelines using any other technology." A magnetometer, for example, would not have been able to locate the pipeline because the maximum depth at which it can detect an object typically is 2 m.

The SBI was able to clearly image a buried 30-in. concrete clad pipe . (Images courtesy of PanGeo)
How it works
The SBI flies 3.5 m from the seabed, imaging an 8-m (26-ft) wide swath that is coarse-rendered to a 5-m by 5-m image made up of voxels sized at 15 by 15 by 10 cm that are constantly being updated with live data. Once a given section is surveyed, the data are rendered using smaller 5 by 5 by 5 cm voxels, a process that enables the detection of smaller objects. With the fine rendering, the SBI was able to locate an item that was not on any of the drawings: a 7.5-cm electrical cable with a smaller steel cable attached at a depth of 1.5 m.
In addition to removing the two lengths of buried pipelines, the operator had requested that an attempt be made to confirm the location of a life-of-field seismic array with 19- and 35-mm diameter cables linked together with hydrophones that they knew was buried beneath the seafloor.
"It was highly unlikely that we could see the cables (with the SBI)," Fleming said, "but the hydrophones were of sufficient size. We knew where it was laid, so when we flew over a small test section, we didn't see it in real time, but we saw the hydrophones in post-processing (when the image was rendered to 5 by 5 by 5 cm). The client was extremely happy with the operation."
PanGeo anticipates the SBI technology will prove its merit further in varied applications in the future, having shown its worth in its inaugural deployment in the North Sea.
Recommended Reading
Enchanted Rock’s Microgrids Pull Double Duty with Both Backup, Grid Support
2025-02-21 - Enchanted Rock’s natural gas-fired generators can start up with just a few seconds of notice to easily provide support for a stressed ERCOT grid.
US Oil and Gas Rig Count Rises to Highest Since June, Says Baker Hughes
2025-02-21 - Despite this week's rig increase, Baker Hughes said the total count was still down 34, or 5% below this time last year.
Devon, BPX to End Legacy Eagle Ford JV After 15 Years
2025-02-18 - The move to dissolve the Devon-BPX joint venture ends a 15-year drilling partnership originally structured by Petrohawk and GeoSouthern, early trailblazers in the Eagle Ford Shale.
E&P Highlights: Feb. 18, 2025
2025-02-18 - Here’s a roundup of the latest E&P headlines, from new activity in the Búzios field offshore Brazil to new production in the Mediterranean.
Baker Hughes: US Drillers Add Oil, Gas Rigs for Third Week in a Row
2025-02-14 - U.S. energy firms added oil and natural gas rigs for a third week in a row for the first time since December 2023.
Comments
Add new comment
This conversation is moderated according to Hart Energy community rules. Please read the rules before joining the discussion. If you’re experiencing any technical problems, please contact our customer care team.