A weekend court ruling has temporarily blocked winter construction at a huge ConocoPhillips oil project on Alaska’s North Slope.
U.S. District Court Judge Sharon Gleason issued an order Feb. 6 barring ConocoPhillips from starting planned gravel mining and gravel-road construction at its Willow project. With an estimated 590 million barrels of oil and the potential to produce 160,000 barrels per day, Willow would be the westernmost operating oil field in Arctic Alaska. First oil is planned as early as 2024, according to ConocoPhillips.
Gleason’s injunction came in response to an environmental lawsuit claiming the Trump administration’s Willow approval failed to properly consider wildlife and climate-change impacts. The judge last week rejected environmentalists’ request for a more sweeping injunction. Her new order halts gravel-related work until at least Feb. 20, giving the 9th Circuit Court of Appeals time to weigh in.
ConocoPhillips had intended to start blasting gravel on Feb. 12, according to Gleason’s order.
The plaintiffs have shown “there is a strong likelihood of irreparable environmental consequences once blasting operations commence,” the order said. Additionally, the plaintiffs’ arguments concerning climate change “could well be likely to succeed on the merits” at the appeals court, Gleason said.
Gleason’s order does not stop construction of seasonal ice roads, which melt away in summer.
Plaintiff representatives noted that Biden is reviewing Trump administration oil policies, including the approval of Willow.
“We’re hopeful this terrible project can be stopped, either by the courts or the Biden administration’s review,” Kristen Monsell, an attorney with the Center for Biological Diversity, said in a statement on Feb. 7.
ConocoPhillips Alaska spokeswoman Rebecca Boys said by email that the company does not comment on pending litigation.
Recommended Reading
Brookfield Sells Pipeline Stake to ArcLight for Exit Totaling $1.7B
2025-03-22 - Kinder Morgan will continue as Natural Gas Pipeline Co. of America’s operator following Brookfield Infrastructure’s sale of a 25% stake to Arclight Capital Partners.
Superhot Rock Drillers Advance Technology to Rival Oil and Gas
2025-03-21 - Building on synergies with the oil and gas sector, geothermal companies seek to go hotter and deeper to unleash energy.
Exclusive: India’s Cairn to Deliver First Shale Well in Summer
2025-03-21 - India's Cairn Oil & Gas, part of Vedanta Group, plans to deliver its first shale well using U.S. shale techniques honed by oilfield service companies, in June or July.
Energy Transition in Motion (Week of March 21, 2025)
2025-03-21 - Here is a look at some of this week’s renewable energy news, including a move by U.S. President Donald Trump to boost domestic production of critical minerals.
Shell Takes FID on Gato do Mato Project Offshore Brazil
2025-03-21 - Shell Plc will be the operator and 50% owner, with Ecopetrol holding 30% interest and TotalEnergies 20%.