Dominion Energy Inc. said on Dec. 16 it was confident it will complete the proposed $7.3-$7.8 billion Atlantic Coast natural gas pipeline from West Virginia to North Carolina by early 2022, in response to a prediction by investment bank Morgan Stanley that a court decision would likely scuttle the project.
“We remain committed to completing the project for the good of our economy and the environment,” Dominion spokesman Aaron Ruby said, noting the company expected to complete construction in late 2021 with final in-service in early 2022.
Dominion made its comments after Morgan Stanley said in a report that “Atlantic Coast will likely not be completed given the Fourth Circuit’s likely (in the bank’s view) rejection, for the third time, of a newly issued Biological Opinion and Incidental Take Statement that we expect to come by the first quarter of 2020.”
In July, the U.S. Fourth Circuit Court of Appeals vacated the Fish and Wildlife Service’s (FWS) second Biological Opinion because the court found the agency’s decisions were arbitrary and would jeopardize the Rusty Patched Bumble Bee and other endangered species.
Federal agencies use Biological Opinions when authorizing projects that could adversely affect threatened or endangered species or critical habitats, and issue take statements to limit the number of those species that could be harmed.
Ruby said Dominion expects the FWS will issue a new Biological Opinion in the first half of 2020.
Appalachian Trail Issue
Dominion suspended construction of the 600-mile project in December 2018 after the Fourth Circuit stayed the FWS’ second Biological Opinion.
Dominion and its partners, Duke Energy Corp. and Southern Co., are also working through a dispute over where the pipeline can cross the Appalachian Trail.
The U.S. Supreme Court has agreed to take up the Appalachian Trail case, which is also important for the construction of EQM Midstream Partners LP’s Mountain Valley gas pipe from West Virginia to Virginia.
Analysts at Height Capital Markets said they expect the Supreme Court will issue a ruling in May or June 2020.
Analysts at Morningstar said they expect the Appalachian Trail dispute will be resolved by a favorable Supreme Court decision or an administrative or legislative solution.
Costs Could Rise
Morningstar said a route revision was the likely compromise for the endangered species dispute but noted that could boost the project’s costs to around $8 billion and push completion into 2022.
When Dominion started work on the 1.5 billion cubic feet per day pipe in the spring of 2018, the company estimated it would cost $6.0-$6.5 billion and be completed in late 2019.
Recommended Reading
Venture Global LNG Files Paperwork for IPO
2024-12-20 - Venture Global LNG filed initial paperwork for an IPO on Dec. 20, about a week after the company’s Plaquemines LNG facility started production.
Dividends Declared Week of Dec. 16
2024-12-20 - As fourth-quarter 2024 nears its end, here is a compilation of dividends declared from select upstream, midstream and service and supply companies.
Rising Phoenix Names Executive as New Director of Capital
2024-12-19 - Rising Phoenix Capital appointed Ben Fujihara, a tenured financial executive, to oversee the company’s capital strategy, investor relations and business development.
Natron Energy Appoints New CEO
2024-12-17 - Sodium ion battery technology company Natron Energy has appointed Wendell Brooks as the company’s new CEO to lead growth initiatives in 2025.
NOV Appoints Former Denbury CEO Chris Kendall to Board
2024-12-16 - NOV Inc. appointed former Denbury CEO Chris Kendall to its board, which has expanded to 11 directors.