Dominion Energy Inc. said on Dec. 16 it was confident it will complete the proposed $7.3-$7.8 billion Atlantic Coast natural gas pipeline from West Virginia to North Carolina by early 2022, in response to a prediction by investment bank Morgan Stanley that a court decision would likely scuttle the project.
“We remain committed to completing the project for the good of our economy and the environment,” Dominion spokesman Aaron Ruby said, noting the company expected to complete construction in late 2021 with final in-service in early 2022.
Dominion made its comments after Morgan Stanley said in a report that “Atlantic Coast will likely not be completed given the Fourth Circuit’s likely (in the bank’s view) rejection, for the third time, of a newly issued Biological Opinion and Incidental Take Statement that we expect to come by the first quarter of 2020.”
In July, the U.S. Fourth Circuit Court of Appeals vacated the Fish and Wildlife Service’s (FWS) second Biological Opinion because the court found the agency’s decisions were arbitrary and would jeopardize the Rusty Patched Bumble Bee and other endangered species.
Federal agencies use Biological Opinions when authorizing projects that could adversely affect threatened or endangered species or critical habitats, and issue take statements to limit the number of those species that could be harmed.
Ruby said Dominion expects the FWS will issue a new Biological Opinion in the first half of 2020.
Appalachian Trail Issue
Dominion suspended construction of the 600-mile project in December 2018 after the Fourth Circuit stayed the FWS’ second Biological Opinion.
Dominion and its partners, Duke Energy Corp. and Southern Co., are also working through a dispute over where the pipeline can cross the Appalachian Trail.
The U.S. Supreme Court has agreed to take up the Appalachian Trail case, which is also important for the construction of EQM Midstream Partners LP’s Mountain Valley gas pipe from West Virginia to Virginia.
Analysts at Height Capital Markets said they expect the Supreme Court will issue a ruling in May or June 2020.
Analysts at Morningstar said they expect the Appalachian Trail dispute will be resolved by a favorable Supreme Court decision or an administrative or legislative solution.
Costs Could Rise
Morningstar said a route revision was the likely compromise for the endangered species dispute but noted that could boost the project’s costs to around $8 billion and push completion into 2022.
When Dominion started work on the 1.5 billion cubic feet per day pipe in the spring of 2018, the company estimated it would cost $6.0-$6.5 billion and be completed in late 2019.
Recommended Reading
Woodside Reports Record Q3 Production, Narrows Guidance for 2024
2024-10-17 - Australia’s Woodside Energy reported record production of 577,000 boe/d in the third quarter of 2024, an 18% increase due to the start of the Sangomar project offshore Senegal. The Aussie company has narrowed its production guidance for 2024 as a result.
Exxon, Chevron Beat 3Q Estimates, Output Boosts Results
2024-11-01 - Oil giants Chevron and Exxon Mobil reported mixed results for the third quarter, with both companies surpassing Wall Street expectations despite facing different challenges.
Record NGL Volumes Earn Targa $1.07B in Profits in 3Q
2024-11-06 - Targa Resources reported record NGL transportation and fractionation volumes in the Permian Basin, where associated natural gas production continues to rise.
Carbon Removal Company Equatic Appoints New CEO
2024-11-18 - Equatic appointed a new CEO in preparation to launch the world’s largest ocean-based carbon removal plant.
Optimizing Direct Air Capture Similar to Recovering Spilled Wine
2024-09-20 - Direct air capture technologies are technically and financially challenging, but efforts are underway to change that.