U.S. energy company Dominion Energy Inc. said July 31 it took a $2.8 billion charge in the second quarter related to the cancellation of the Atlantic Coast natural gas pipeline from West Virginia to North Carolina.
Atlantic Coast was the most expensive U.S. gas pipeline under construction when Dominion and partner Duke Energy Corp. exited the $8 billion project earlier this month due to regulatory uncertainty following years of delays and billions of dollars of cost overruns.
RELATED: Dominion, Duke Energy Cancel Atlantic Coast Pipeline
Atlantic Coast is just one of several U.S. oil and gas pipelines mired in legal and regulatory battles with local and environmental groups that have found numerous problems with U.S. permits issued by Trump administration agencies.
When Dominion started work on the 600-mile (966 km) pipe in the spring of 2018, the company estimated it would cost $6.0 billion to $6.5 billion and be completed in late 2019.
In the weeks before canceling the project, however, Dominion said it could finish the project in early 2022 only if it received new federal permits soon that would survive court challenges.
In addition to regulatory delays, Atlantic Coast was also hurt by a short-term hit to gas demand from the coronavirus and a longer-term hit from growing consumer interest in more clean energy projects.
Virginia is one of several states seeking to achieve 100% carbon-free power over the next two decades.
Even though gas is the cleanest fossil fuel and is considered by many energy analysts to provide a bridge from dirty coal to clean renewables, it still produces carbon.
Dominion has plans to invest up to $55 billion over the next 15 years on zero-carbon generation, energy storage, gas distribution replacement and renewable natural gas.
Dominion said it aims to achieve net-zero carbon dioxide and methane emissions from its power generation and gas infrastructure operations by 2050.
Recommended Reading
Brookfield Sells Pipeline Stake to ArcLight for Exit Totaling $1.7B
2025-03-22 - Kinder Morgan will continue as Natural Gas Pipeline Co. of America’s operator following Brookfield Infrastructure’s sale of a 25% stake to Arclight Capital Partners.
Apollo Acquires BP’s Gas Pipeline Stake for $1B
2025-03-21 - BP Pipelines holds a 12% interest in the Trans-Anatolian Natural Gas Pipeline (TANAP), which transports natural gas from Azerbaijan across Turkey.
Energy Transfer Prevails Against Greenpeace, Wins $660MM in Damages
2025-03-20 - A jury in North Dakota has ruled in favor of Energy Transfer with a $660 million blow to environmental group Greenpeace.
Canadian Province Gives Environmental Warning to Pipeline Project
2025-03-19 - The Prince Rupert Gas Transmission Project is a 497-mile project that would ship up to 3.6 Bcf/d of natural gas to an LNG facility on the Canadian west coast.
Cheniere’s Corpus Christi 3 Ready to Begin LNG Production
2025-03-17 - Cheniere’s Corpus Christi LNG Stage 3 expansion project produced its first LNG in December.